Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Progress Bar Thunder Bar

15 replies [Last post]
Hemanth Kumar
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 1 Nov 2002
Posts: 260
Groups: None
Hi All

Can We Customise The Progress Bar

I feel The Line Is Too Thin I Want A Thicker One


Hemant

Replies

Nicolas Igersheim
User offline. Last seen 7 years 47 weeks ago. Offline
Joined: 25 Jun 2007
Posts: 62
Let me expatiate a little:

In my branch, oil gas and the like
at a certain stage during the project,
the engineer issues several orders or contracts
to several suppliers or contractors.
These are then compelled contractually
to deliver or to operate at dates or periods according to planning.

The cotton line allows the engineer to focus on those
tasks that endanger the sequential flow of work
and to correct the situation before a given contractor (an electrician) appears on
the site at the contractual date only to find out
that the electric substation is not yet ready for him...
If you "update" your planning with the delay on the
substation, then the electrician is not due for another month
and that would be misleading, because he is, "contractually".

I hear some of you utter the word "baseline",
but a simple gannt is a tough enough chart to read;
if you add the initial bars, nobody will be able
to decipher it among the construction or the direction teams...
James Griffiths
User offline. Last seen 15 years 46 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None
Brad - it’s just nice to read such well-articulated replies that often echo one’s sentiments. However, if I consider anyone’s replies to be load of moopoo, even Trevor’s, then I’ll respond accordingly.

James.
Brad Lord
User offline. Last seen 10 years 25 weeks ago. Offline
Joined: 27 May 2003
Posts: 256
Groups: None
james

you just seemed so dont know in love with trevors responses

ha ha ha
James Griffiths
User offline. Last seen 15 years 46 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None
Come hither, Bradley, young man! Fences - either side. Batting - both sides. Jar of swarfega - give it go (as long as it’s the green stuff, and not the ultra-coarse yellow.)
Brad Lord
User offline. Last seen 10 years 25 weeks ago. Offline
Joined: 27 May 2003
Posts: 256
Groups: None
james

you sound like you fancy trevor, come on leonard were going

ha ha ha
James Griffiths
User offline. Last seen 15 years 46 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None
Here, here, Trevor.
Trevor Rabey
User offline. Last seen 2 years 5 days ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
Nicolas, fair call but you have put quotes around things that I didn’t actually say.
As far as I know, there is no way to change the appearance of the progress lines except via Tools, Tracking, Progress Lines, Line Styles, and changing the weight of the line just isn’t there.

It is a case of
a) I cannot give you what you want because as far as I know, and I am pretty sure I know about this but I could be wrong, it doesn’t exist.
b) I am pretty sure I know about this but I could be wrong.
c) in my opinion, progress lines serve very little purpose d) I suggest that you might like to consider the possibility that you dont need it, because it, along with other formatting "nice to haves" is not very important compared to other priorities such as getting the modeling and tracking right.
e) but you can choose to continue to need it and search for a solution, which might exist but see a) and d) above).

You said:

"The progress bar, thunder bar or cotton line
is not so useless if you leave your Gannt
the way you planned it initially
i.e. not as built."

... but this is never supposed to happen, since the tracking and updating is the whole point of doing the planning in the first place. You say it is not useless, but what is it useful for? At most, this would just be an intermediate step immediately before moving unused duration to to the right of the Status Date and progress in the future back to the left of the Status Date. The zig-zag line is slightly useful to indicate Tasks where this has to be done to iron out the zigs and zags, but once they are gone there is no further need for it, and its appearance for this limited purpose doesn’t matter.
Nicolas Igersheim
User offline. Last seen 7 years 47 weeks ago. Offline
Joined: 25 Jun 2007
Posts: 62
Hi everyone,

Well but if this isn’t a typical case of
"tell me about what you need, and I will
explain how you can do without"
It is a case of
"I cannot give you what you want but I know
a) what I am doing
b) that you dont need it"

The progress bar, thunder bar or cotton line
is not so useless if you leave your Gannt
the way you planned it initially
i.e. not as built.

And I confirm, it is too thin!
Anybody found a way to thicken it?

btw: since I do not have the honor of being Japanese,
I enjoy being French .
Trevor Rabey
User offline. Last seen 2 years 5 days ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
Absolutely correct.
It’s always nice to find that I agree with someone.
Once upon a time in the newsgroup microsoft.public.project this came up and everyone who knows what they are doing says the same thing.
http://groups.google.com/group/microsoft.public.project/search?group=mic...
Rod Gill and Gerard said that Microsoft only put them in because someone in Japan wanted it, because it resembled doing Gantt Charts with coloured paper tape and elastic progress lines with pins.
The MSP help says that they measure progress. They don’t.
If the line zigs to the left, that means there is unused Duration that needs to be moved to the right of the Status Date (Re-schedule Work Button on the tracking Toolbar). If the line zags to the right, that means that there is duration elapsed in the future (of the Status Date), which is just plain impossible, and that should all be moved back to the left of the Status Date. When everything has been updated and re-scheduled there should be no zig-zag.
James Griffiths
User offline. Last seen 15 years 46 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None
You really don’t want to use the "progress bar/line". It has been one of the most useless functions I’ve ever come across, and I’ve never been able to predict what it will do or interpret the reason why it has done it.

James.
Hemanth Kumar
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 1 Nov 2002
Posts: 260
Groups: None
Dear Chris

Thunder bar is actually a lightening bar,
which shows activities delay/Ahead status in a snapshot
Right Click bar area select progress bars.
Chris Oggham
User offline. Last seen 9 years 48 weeks ago. Offline
Joined: 20 May 2004
Posts: 605
Groups: None
Hemant,

What is a Thunder Bar? You set up the thread, suppose you tell us.

Chris Oggham
Hemanth Kumar
User offline. Last seen 1 year 21 weeks ago. Offline
Joined: 1 Nov 2002
Posts: 260
Groups: None
Dear Andrew

You Missed The Bus

What Is A Thunder Bar ?

Dear Trevor
Your Bus Is Not My Bus

Hemant
Andrew Owenson
User offline. Last seen 16 years 30 weeks ago. Offline
Joined: 10 Nov 2005
Posts: 48
Groups: None
Hameth

Goto Format Bar Styles its in there, just choose a thicker bar, the default is to colour the top half.

Best Wishes

Andrew
Trevor Rabey
User offline. Last seen 2 years 5 days ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
Progress bars suck and serve no useful purpose. better to not bother.