Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Roll Up Resource Names

4 replies [Last post]
Neil Gartland
User offline. Last seen 15 years 1 week ago. Offline
Joined: 1 Mar 2010
Posts: 7
Groups: None
Is it possible within the Resource Names column, to roll up resource names to summary tasks so that if three resources had been used on different tasks in a group, these three names would be displayed on the summary line in the resouce names column.

I know it is possible to access this information through other views but want to know if it is possible to customise this view?

Any assistance appreciated

Thanks

Replies

Rafael Davila
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
MAYBE THIS IS WHAT YOU ARE LOOKING FOR.

Format the bar chart portion of a Gantt view:

http://office.microsoft.com/en-us/project/HA012253681033.aspx

Go to Display task names for individual .......

Have some issues with overlapping tasks, unless can be fully resolved I would avoid using this at all.

Roll up resources

Hope this helps.

R. Davila
Neil Gartland
User offline. Last seen 15 years 1 week ago. Offline
Joined: 1 Mar 2010
Posts: 7
Groups: None
Thanks Alexandre, good point about rolling up to the Resource Names column, do you know where I might find an example of a macro that would do this please?

Thanks