Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Programmed S-Curve

4 replies [Last post]
Jhorbam Baena Orozco
User offline. Last seen 2 years 40 weeks ago. Offline
Joined: 14 Sep 2009
Posts: 75
Groups: None
Hi...How can i get the programmed s-curve from Microsoft Project?...

Thanks

Replies

Trevor Rabey
User offline. Last seen 1 year 43 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
S Curve comes in different flavours.
Its a graph, it has axes, you have to know what you want on them.
Time is on the horizontal axis.
What do you want on the vertical axis, Cumulative Cost or Work?
You can get Cumulative Cost and Cumulative Work at Reports, Visual Reports.
Jhorbam Baena Orozco
User offline. Last seen 2 years 40 weeks ago. Offline
Joined: 14 Sep 2009
Posts: 75
Groups: None
Yes... I know that it is possible in MP2003 but...i used MP2007...i refer to Programmed S-Curve..to the initial proyection of how the s-curve must be run agree the initial plan. The curve against we compare the curve of execution.

I hope that you understand my question...cause i don’t have a lot of practice in my english.

Thanks
Trevor Rabey
User offline. Last seen 1 year 43 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
When you say "s-curve", you mean Cumulative Cost or Cumulative Work?
Either one, in MSP2003 View, Toolbars, Analysis Toolbar and then the "Analyse Timescaled data in Excel" button, then follow the wizard.