PROGRESS UPDATION PROCESS

1 reply [Last post]
Khaja Sharief
User offline. Last seen 10 years 50 weeks ago. Offline
Joined: 9 Sep 2008
Posts: 44
Hi,
I have a very basic doubt regarding how to register progress in MSP, just about the methodology.

Initial data: project schedule is prepared, base line is saved.
Case-1:
Suppose there is an ’X’ activity in the schedule with a duration of four days (day1,day2,day3,day4).

Consider the frequency of progress entry is daily.

Now the activity has started as per schedule on day1 and I was reported a progress of 10%,
Again on day2, I was reported the progress of 30%
Again on day3, I was reported the progress of 75%
Again on day4, I was reported the progress of 100%

Question:
1.How do you register progress daily in MSP on daily basis ?.
2.How can we get the progress report date wise for the particular activity-X ?.

Can anyone please let me the process. Thanks in advance.