Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Problem with resource pool

1 reply [Last post]
Chris Murray
User offline. Last seen 16 years 2 days ago. Offline
Joined: 17 Apr 2007
Posts: 4
Dear All,

I’ve currently got a schedule with 4 consolidated schedules within it, each using a resource pool. The resource pool works fine for the first 3 and doesn’t seem to work for the last schedule within.

The usual steps have been taken, i.e. assigning the resource pool to the schedule.

Once again after this step it does not show the resource pool assignments?

HELP!

Replies