Hi Asif,
I saw you posted the same post in P3.
I dont know what software you are using.
Anyway the concept is the same.
the quantity you mention is called resource in both software
First you need to define resource, then assign the resoruce to task/activity, then update resource with acutal value.
For detail steps, see help file for resource
I have to assign quantity to the task. Like plaing concrete 100 cum
hi Asif ,
Do you mean how to assign resources to task ?