fix cost for all project

1 reply [Last post]
ersin namli
User offline. Last seen 12 years 5 weeks ago. Offline
Joined: 19 Jul 2005
Posts: 54
Groups: None
Hi, how can i identfy a daily fix cost for whole project in ms project.
can i adjust the max. min. crew size in resource leveling
thanks for your answers

Replies

Create dummy resource with the project daily rate and assign it to the whole project.
Max/min resource requirements are not supported by this software.