Ive used project for a number of years and usually, with a bit of pain, found ways to get it to do what I want. But Im struggling with this one:
I just want to know, what is the estimated end date, based on:
1. Project start date
2. Tasks % complete.
For example, I have a project with 3 one day tasks, same resource. If I start Monday, then it will finish end Wednesday. But, if the current date is Tuesday, and no tasks have been started, the estimated complete date will be end Thursday. Also, if the current date is Monday, but any one of the 3 tasks is already done, the estimated end date is end of Tuesday.
Until now, Ive controlled progress by removing remaining time / tasks as the work is done, and set a new start date of today.
But Id like to show all tasks with % complete, with est end date.
Seems like this is one of the most fundamental things you would need to do with project, I must be missing something completely.
Any help much appreciated
Replies