using weight

1 reply [Last post]
Jafar Zarei
User offline. Last seen 15 years 12 weeks ago. Offline
Joined: 6 Jul 2003
Posts: 5
Groups: None
Hi Planners,

I want to give weight to all tasks in MS PROJECT that effects on progresses(%complete)
It means I want to have the progress according to the weight not duration.
Please help how?
Thank you



Replies

MK TSE
User offline. Last seen 4 years 25 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Use a custom field to store the value of weighting. Copy the required columns from Project to X-L, calculate the progress according to the weighting factor. Copy and paste the progress back to Project.

(btw, if formula is allowed in Project, no X-L required)