|
making a claim |
8
|
by Rola Sabbah 4 Mar 2010 - 15:00 |
by Samer Zawaydeh 8 Mar 2010 - 00:56 |
|
BIM Forensic Delay Analysis with 3d impacted models |
10
|
by Matthew Edwards 28 Jan 2010 - 08:32 |
by Samer Zawaydeh 6 Mar 2010 - 15:56 |
|
EOT on contractual milestone |
9
|
by ashraf mokhtar 31 Dec 2009 - 05:48 |
by Mike Testro 4 Mar 2010 - 08:51 |
|
NEC3 with Target Cost. |
4
|
by muhammad anwar 1 Mar 2010 - 12:32 |
by Gary Whitehead 2 Mar 2010 - 05:20 |
|
Excessive Revised Construction Drawings |
3
|
by Raphael Adeyemi, ... 30 Dec 2009 - 05:39 |
by Mike Testro 28 Feb 2010 - 09:59 |
|
Scope Creep-Silver and Yellow Book of FIDIC |
4
|
by Francis Moyalan, ... 15 Feb 2010 - 04:58 |
by Samer Zawaydeh 16 Feb 2010 - 08:00 |
|
Contractor’s delays |
14
|
by Ahmad Albirawi 7 Feb 2010 - 07:40 |
by Ahmad Albirawi 10 Feb 2010 - 02:03 |
|
Extraction licence -foreseeable requirement? |
4
|
by Gary Whitehead 9 Feb 2010 - 04:17 |
by Andrew Flowerdew 9 Feb 2010 - 10:41 |
|
Is there any difference |
5
|
by Shah. HB 11 Jan 2010 - 13:14 |
by Trevor Rabey 12 Jan 2010 - 01:02 |
|
Methods of Impact Analysis |
11
|
by Shareef Abdul Azeez 31 Dec 2009 - 05:33 |
by Shah. HB 6 Jan 2010 - 02:14 |
|
What is start date LOA or Kick off |
14
|
by Santhosh kumar Na... 14 Dec 2009 - 04:31 |
by Samer Zawaydeh 31 Dec 2009 - 10:28 |
|
EOT Claim - Contractor not providing electronic copy |
22
|
by Vamsi Gollapinni 9 Dec 2009 - 01:17 |
by Andrew Flowerdew 30 Dec 2009 - 16:15 |
|
Engineers review period clause no? |
6
|
by Santhosh kumar Na... 9 Dec 2009 - 04:06 |
by Raphael Adeyemi, ... 30 Dec 2009 - 05:47 |
|
Nominatation and Commencement Date |
11
|
by Rami Al Haddad 15 Nov 2009 - 09:07 |
by Samer Zawaydeh 29 Dec 2009 - 13:42 |
|
contractual milestone |
3
|
by ashraf mokhtar 29 Dec 2009 - 08:24 |
by Samer Zawaydeh 29 Dec 2009 - 13:33 |
|
DRAFT CONTRACT AGREEMNT |
4
|
by Umer Mehmood 23 Dec 2009 - 06:42 |
by Raphael Adeyemi, ... 29 Dec 2009 - 00:40 |
|
Advice |
17
|
by Catherine Barthelemy 27 Nov 2009 - 09:00 |
by Toby Hunt 18 Dec 2009 - 03:34 |
|
Nominated subcontractors |
1
|
by Samad Mohd Abdul 16 Dec 2009 - 03:46 |
by Samer Zawaydeh 16 Dec 2009 - 10:32 |
|
Revised and Recovery Programs |
13
|
by Abdallah Abu Ghaz... 6 Dec 2009 - 07:20 |
by Samer Zawaydeh 9 Dec 2009 - 00:59 |
|
Claims Critical Path |
8
|
by James Young 25 Nov 2009 - 09:18 |
by Rafael Davila 7 Dec 2009 - 08:00 |
|
EOT award not accepted |
5
|
by Chris James 12 Nov 2009 - 03:33 |
by Samer Zawaydeh 29 Nov 2009 - 14:26 |
|
Boq Description its mentioned the thickness |
3
|
by Balachandran Kand... 21 Nov 2009 - 08:06 |
by Samer Zawaydeh 29 Nov 2009 - 14:07 |
|
Extension of Insurance Policies |
1
|
by Sajid Balma 25 Nov 2009 - 04:28 |
by Samer Zawaydeh 29 Nov 2009 - 13:58 |
|
E.O.T Claim |
2
|
by James Young 26 Nov 2009 - 14:14 |
by Samer Zawaydeh 29 Nov 2009 - 13:50 |
|
contract |
3
|
by divakar babu 25 Nov 2009 - 09:21 |
by Samer Zawaydeh 29 Nov 2009 - 13:23 |