I was involved in a contract of luxirious private development that was contracted on FIDIC 87 Edition which is meant for contract with substantia design before final contract formulation.
In the course of the project, there were several designs or drawing review, there was a particulatr that was reviewed 34times for a contract that supposed to finish within 9months.
Secondly, there was a huge provisional sums included in the contract which the Client Project manager erroneously treated as Prime Cost items...., the works related were issued through Engineers Instructions as Nominated Subcontract. The resulted to significant delay
Thirdly,in the course of project progression, there were other Consultants on board not mentioned in the Tender and Contract documents. This resulted in communication gap in getting necessary approvals and drawings review.
Fourthly, the PM was performing the roles of an Engineer, by all means according to FIDIC, he is not
The Project was substantia delay and EOT was submitted which the PM recieved and declined action for over 3months.
Could you guys advise me what to do
Cheers
Replies