Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Aren't "windows" delay analysis flawed by the common condensing of schedule as schedule goes on?

2 replies [Last post]
John Reeves
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Aren't "windows" delay analysis flawed by the common condensing of schedule as schedule goes on?  -  Do if the project is complete and you have 5 delays at 20 days each, but he job is only 20 days late - couldn't you just prorate each delay - because none should get credit for other changes to bring it back onto "close to"  schedule?

Replies

John Reeves
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Thank you very much for the comment, that is what makes this site great!  I am dealing with a contractor doing Windows analysis and the total of the Windows adds to up to more than the project is delayed.  Not sure yet, if it is concurrency, logic changes or yet, but that is why I asked if a contractor should be given the day "due" or the days "necessary" when it is showing less.

Patrick Weaver
User offline. Last seen 5 days 17 hours ago. Offline
Joined: 18 Jan 2001
Posts: 383
Groups: None

The 'windows' approach to delay analysis is supported by AACEi and many legal precedents. BUT the delay within the time window does need to be shown to cause a delay to the completoin of the project: Costain Limited -and- Charles Haswell & Partners Limited 2009] EWHC B25 (TCC). See: https://mosaicprojects.com.au/PDF_Papers/P035_Assessing_Delays.pdf