Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Withdrawal by Contractor in the early stage

3 replies [Last post]
Kannan CP
User offline. Last seen 19 weeks 14 hours ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi All,

After the award of Contract and just after the mobilisation time period, the Contractor sent letter to Client stating that they are unable to carry out the works due to some internal issues in the Organization. Also they want a no future claim letter from the Client and not interested to take the money for mobilisation stage (less amount).

In this case with which clause of FIDIC the client can claim (if he intended). and what are the possible scenarios of negotiation for closing this issue. Definitely the Client wants to carry out this Project.

Best Regards

Kannan

Replies

Kannan CP
User offline. Last seen 19 weeks 14 hours ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Thanks Mike and Patrick.

Patrick Weaver
User offline. Last seen 5 days 20 hours ago. Offline
Joined: 18 Jan 2001
Posts: 383
Groups: None

The most expeditious way forward would be:

1) To accept the termination by the contractor, holding them liable. If the withdrawl is genuine you don't want them on the project. 

2) Relet the contract expiditiosly (maybe negotiate with the 2nd and 3rd tenderes from the original bid).

3) When the full cost and time consequences are determined, seek compensation from the defaulting contractor.

HOWEVER, this is a matter that requires local expert knowledge of the law and careful consideration of the risks - the client ultimately needs the project and will not nescesarily recover anything from the defaulting contractor. A negotiated outcome is likely to be the lowest cost and risk to the client: https://www.mosaicprojects.com.au/WhitePapers/WP1024_Negotiating.pdf

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Kannan

Wrongful termination by the contractor.

Best regards Mike Testro