Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Recovery Schedule and EOT Claim Analysis

5 replies [Last post]
Kannan CP
User offline. Last seen 19 weeks 3 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi All,

As specified in Fidic Contracts, if the Contractor failed to meet the progress rate as agreed in the approved Baseline Schedule, he needs to submit a recovery schedule, elaborating how he intends to recover his delays and bring the Project back on track.

1. Is the Recovery Schedule to be approved, or just to accept it based on the Contractor's revised sequence/methodology/additional resources etc, for the progress monitoring purpose?

2. If any new claims araised (after this recovery schedule), which schedule to be followed for the EOT analysis- original approved baseline or the approved/accepted recovery schedule?

3. Is there any accepted guidelines like SCL Protocol,  which specifies which schedule to be followed?

BR

Kannan

Replies

Kannan CP
User offline. Last seen 19 weeks 3 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Thanks Mike and Anoon

BR

Kannan

Anoon Iimos
User offline. Last seen 2 years 45 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Perhaps the first question would be: What triggers the need for a recovery schedule? Succeeding questions are: To whom the delays would be attributable to? If the delay is caused by "Act of God", or "Force Majeure" caused by humans, then who shall pay? The need for a recovery schedule comes with lots or endless questions, into which perhaps may lead back to the original schedule. For me, a recovery schedule means to create a new baseline schedule, hence, all issues/disputes must be settled first from the original baseline schedule, otherwise, how can you agree with a recovery schedule?
Mike Testro
User offline. Last seen 36 weeks 7 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Kannan

It is always good proactice to record progress on the original baseline programme.

You may need to do it again on the mitigated programme.

Best regards

Mike Testro

Kannan CP
User offline. Last seen 19 weeks 3 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi Mike,

By having an approved recovery programme (revised baseline) with the Contractor's mitigation action in it, can we stop reporting the progress based on the original baseline programme, which is no more relevent to site sequence? or is there any contractual implication by doing so.

BR

Kannan

Mike Testro
User offline. Last seen 36 weeks 7 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Kannan

If the Contractor has mitigated his own delay and this is set down in the new approved programme then tah should be the baseline for any new releavnt events after the acceptance of the programme.

If however the delay has been seen to be before the revised programme then the event should be impacted on the original programme. It may then arise that the mitigated programme was not needed.

Best regards

Mike Testro