My appology if this one has been discussed before.
I am in the middle of discussion with my clkient about our entitelment for an extension of time.
Our client asked us to send our price for extera work that was needed for an equipment installation work and instructed us to not to proceed for further work except receiving another direction by company to proceed. Atthe poit of time the equipment was landed and we hold the job. The date for landing was 20th Aug, and the latest start was 10th Sep. we hold the work and resequenced the front work due to client instruction for holding the job. We received next direction much later from the client to proceed.
for my delay impact analysis I selected the most recent updated schedule with the data date before 20th Aug. However, our client beilieve I should select the most updated schedule prior to 10th Sep (our late start date ) when any further delay can make it critical.
Not prety sure what is our entitelment?
Replies