Good morning
I'm new in this forum so, first of all, I want to thank you anyone who will loose a little bit of its time to reply.
I'm actually working for a structural steel company and I'm experincing trouble in reaching an Approved baseline programme.
In particular I've the following issue, which I try to summarise:
The project is composed by several sub-site, almost indipendent one for the other (say building A, B, C, D).
All building are similar to each other.
We need an access date for each of the building, dictaded by the contractor (to simplify I would say we need the concrete foundation to start erect our steel work on top)
As per subcontract programme we have a total period during which we need to complete all the building with a single milestone at the end. Access dates for each building are clearly defined in the contract.
Given the restrain I've built a programme similar to the one below, including same "resource" link and considering the possibility to work with the same resources/crane jumping from building A to C, for example, bearing in mind also a possible learning curve.
Now we are in the current status:
- the Contractor (who is our client, we are a subcontractor) is late in giving access to building A, C, D and he want to postpone access date.
- Contractor mention the following contract clause: "Use of float-suppression techniques (such as preferential sequencing, special lead/lag restraints, extended activity time or imposed dates) shall be cause for rejection of the proposed Baseline Programme and any revision or updates [...]"
Bearing in mind that, as clearly stated in another clause, "free float [...] is jointly owned by both" can he reject the programme using this?
Basically, in his opinion, there is no reason to link Building A with building C, which are indipendent.
In our view the delay in access A, B, C, instead, create a different overlapping between the buildings, obliging us to bring more resources on site (even if for a shorter period). That's not easy as some resoursces (menagement, special trailers, big cranes, etc.) cannot be easily doubled or, at leaste, not for free and we would loose all advantages of learing curves.
We believe the Approved Baseline should reflect the subcontract situation (which we used to price the job) and any delay of the access dates should be managed later on with revised programme and claim (if any and reasonable).
They substain the floats (i.e. between completion of building A and Milestone) belong to everybody so they can move access dates freely as (looking at the single building only) it is not critical.
What do you think about?
(I hope my explanation is clear enough)
Many thanks
Giordano
Replies