Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Claim for EOT and Out of Sequence

1 reply [Last post]
Ritchie Fadrigalan
User offline. Last seen 9 years 32 weeks ago. Offline
Joined: 23 Oct 2011
Posts: 6
Groups: GPC Qatar

Dear PP,

Good day to all. I am having some ambiguity regarding the proper way in analyzing the claims for EOT. I just want to know your opinion if we need to correct the out of sequence activities prior to window analysis?

Your expertise with this matter is highly appreciated.

 

Regards,

Ritchie

Replies

Mike Testro
User offline. Last seen 36 weeks 14 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ritchie

My advice is that as and when you come to a window where an adjustment is needed you do it then.

You will have to save the baseline each time you make an adjustment.

My better advice is don't bother with a windows analysis for a forensic situation - it is a waste of time.

Best regards

Mike Testro