Hi All,
Seeking some advice with regards to an EOT that has been submitted by a Contractor.
The Contractor has impacted the Baseline schedule with employer culpable events to demonstrate his entitlement to an extension of time.
By impacting the baseline with numerous employer events (individually), the Contractor relies upon the event with the greatest impact to justify his EOT.
The Contractor has quoted various court cases such as Henry Boot v Malmaison (1999) as justification to EOT regardless of his own delays.
The Contractor has not claimed for costs related to the delays, prolongation etc
is it possible to rebutt a Contractors claim for time only when he has submitted a delay analysis presented as above.
I feel concurrency is a very Grey area and it may be the case that the Contractor was already in delay prior to any of the Employer events although this cannot be established through the Contractors present analysis.
Thanks in advance
Replies