Hello All,
As this is my 1st posting on PP website I apologise in advance if this question is a repeat of previous posts. I have read quite alot of threads but did not come across one that covered this topic. Not saying it does not exist somehwere.
My question is not so much one of methodology (TIA, As-built vs As-planned etc) but simply of procedure and a fundamental one at that.
When inputting a delay event in a programme (p6) what is the best process? I.e creating a unique bar representing the delay itself linking it to the affected activties or adjusting the start/finish dates of those activties as per the duration of the delay itself and then explain witihin the narrative the impact on the CP etc. are there any other processes for doing this and is it method related?
Obvisouly from my question I am a newcomer to the craft!
Any input is appreciated.
Regards
Aidan