Hello planners,
I have been asked to prepare an EOT claim for a project which is in the handing over stage. Contract duration is 500days and the project end date slipped by an year due to delay in approvals (design, materials) & additional works.
My situation is
1. Baseline is not accepted (although the updated program is attached along with the monthly progress report)
2. Baseline is having 10 non contractual constraints, open ends, faulty links, unecessary lags, Total float (around 200 activites) between 50-265, possibly due to faulty links/constraints.
3. Some of the relevant activites (for eg: design (some), T&C, procurement (long lead-some)) are not in the Critical path (160 activities in the path)
4. The end date of the program inserted with the events is not slipping because of the faulty links.
5. Records for actual dates are not that good.
How to approach in such scenario and prepare an EOT claim. Appreciate your suggestions to tackle this given task.
Thanks.