Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

concurrent delay, who is responsible the contractor or Employer

3 replies [Last post]
Karthik Murugesan...
User offline. Last seen 10 years 23 weeks ago. Offline
Joined: 12 Oct 2006
Posts: 15
Groups: None

Regarding the concurrent delay, who is responsible the contractor or Employer. If a contractor raises the EOT based on concurrent delay with the employer, then what would be the determination reslut? whether employer has to bear the cost or the contractor? as per Fidic.

 

Thanks

 

Karthik

 

Replies

Mike Testro
User offline. Last seen 19 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Karthik

How concurrency is decided depends on the law in your Jursidiction.

UK and commonwealth countries would normallt follow my description.

In other legal systems it may not be so cut and dried.

It is usually best to apply the universal clause 101 - common sense.

Best regards

Mike Testro

Karthik Murugesan...
User offline. Last seen 10 years 23 weeks ago. Offline
Joined: 12 Oct 2006
Posts: 15
Groups: None

Thanks Mike,

That's clear..i believe these are the points the arbitrators consider for any project disputes arising on this...

 

Karthik

Mike Testro
User offline. Last seen 19 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Karthic

As far as I know FIDIC does not mention concurrent delay specifically.

The other problem is that different delay analysis methods give different results on concurrency.

For instance it is almost impossible to generate true concurrency using the windows method.

Currently the generally accepted rules are these:

1. True concurrency - where two delay events each start on the same day and each affect the same critical path.

Example: The employer cannot grant access to start the works and the contractor's selected piling sub-contractor has gone bust.

Now it all depends who solves their problem first - If the contractor has a new piling sub contractor ready to start but the employer still cannot grant access then the total delay is borne by the employer and no LAD's can be applied but the contractor can only claim costs for the time between when he was ready to start and the employer granted access.

Things start to get more complex if different delay events start on different days and / or affect the critical path differently.

2. Mixed concurrency - over riding employers delay

If the employers delay started first and caused the whole of the delay but the contractors event would have caused delay but for the overiding delay then the contractor gets relief from LAD's but does not get costs for his delay period.

3. Mixed concurrency - over riding contractors delay

If the contractors delay starts first and caused the whole of the delay - and the employers delay does not cause any further delay then the LAD's are applied and no costs awared.

If the contractors delay starts first and caused part of the delay - but the employers delay does cause some further delay then the period of further delay is added to the original completion date and an EoT is awarded for the resulting end date. LAD's are deducted for the remaining delay period. It is not clear if the contractor gets costs for the extended period.

It gets really complex when there are multiple delay events all overlapping.

I hope that is clear.

Best regards

Mike Testro