Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

ACTIVITY SCHEDULE FROM NEC3

16 replies [Last post]
Mervilyne Pangan...
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 25 May 2009
Posts: 53
Hi Guys,

I need to know Planners Idea for Activity Schedule.

From my point of view this is just another terminology.
I think its the same with the usual program we are sending after award of contract...

Regards,

Replies

Ross Humphrey
User offline. Last seen 10 years 11 weeks ago. Offline
Joined: 5 Sep 2014
Posts: 5
Groups: None

An activity schedule is a schedule of the contract price and a payment schedule for the aforementioned contract price.

Samer Zawaydeh
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Mervilyne,

You need to make it fun. That way you will enjoy your time and make yourself more productive. In addition, the people around you will be more productive as well.

Don’t be too angry, and consider it as learning experience. Now you can multi-task and next time, you can get take off quantities much faster because of your experience.

With kind regards,

Samer
Mervilyne Pangan...
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 25 May 2009
Posts: 53
Dear Samer,

Yes Sir, not only for zoning but also for materials, breakdown of activities and etc.... the bad part is, Im doing quantity take off as well...

Regards,
Mervilyne Pangan...
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 25 May 2009
Posts: 53
Dear Gentlemen,

Thanks for the shared ideas.

Regards,
Rodel Marasigan
User offline. Last seen 1 day 22 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Dear Mervilyne,

BOQ is more often represented by Schedule of Rate although sometimes there is also lump sum price.

Activity schedule is represented by Schedule of Lump Sum price and sometime called Work package with Lump Sum price in NEC3 or in forms of contract.

Schedule of Activity from the point of Planning and Scheduling view is different from Activity schedule from point contract perspective. Schedule of Activity is more on task on Planning and Scheduling while Activity Schedule is more often a list of Work packages with lump sum price.
Samer Zawaydeh
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Mervilyne,

Using the BOQ will cover most of the items, but you need to use the drawings as well because sometimes you need to divide it by zone or by location, which the BOQ doesn’t take care of.

With kind regards,

Samer
Mervilyne Pangan...
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 25 May 2009
Posts: 53
Dear Gentlemen,

Does it mean that Scheduled BOQ can be activity schedule as well?

Please guide me on correct way of planning. Usually, I am making the BOQ items as my WBS for easy tracking and costing. And then a breakdown of activies from the BOQ items and make a sequence of work...

What about?????

Thanks,
Oliver Melling
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
I agree Samer, it easy to mix up.

If you had a programme of 10,000 activities then a table of activities lose its value.

I think it would be better described as a ’Comparison Table’
Samer Zawaydeh
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Oliver,

Thank you for taking the time to explain it to me. Yes we do that for bigger size projects. It is related to the BOQ items and the price breakdown of each item.

The activities are not discussed at the Tender stage. But it seems that a mixing up of terms is causing a little bit of confusion.

As long as the originator of the question got the answer that they want satisfying the essence of the question, it is ok with us I think.

Thank you again for your kind explanation.

With kind regards,

Samer
Oliver Melling
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
Samer,

IMO, it is a table in the ITT/Contract that breaks the job into specific components and associates a price with each component.

When people tender for the job it is common to base the WBS on the structure of the activity schedule, this way the costs in the programme can be easily transfered into the table.

When the Client receives all the tenders, he/she can look at the the table to see how much each company has costed for each specific component. (Be this a building floor, a design stage or the cost of a discipline)

The table can serve several purposes:
1. It makes it easier to compare like for like costs between bids.
2. It can be the basis for which stage payments are made.

I often think if the people who write tenders (and in particular activity schedules) realised this then the activity table would ask for costs that relate to how the job should be planned, that are all at a similar level in the hierarchy. I often fill them out with one line asking for the cost of checking a specific assembly drawing and the next line asking for the total cost of site works!

I suppose if things made sense and were made simple....everything would be too easy! :D

Regards,
Samer Zawaydeh
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Oliver,

What is the real meaning of Activity Schedule? Why do we need to have something like this.

With kind regards,

Samer
Oliver Melling
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
A schedule activity is in no way the same as an Activity Schedule.
Samer Zawaydeh
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Mervilyne,

As per PMI PMBOK definition:
"
Schedule Activity: A discrete scheduled component of work performed during the course of a project. A schedule activity normally has an estimated duration, an estimated cost, and estimated resource requiremetns. Schedule activities are connected to other schedule activities or schedule milestones with logical relationshops, and are decomposed from work packages."

With kind regards,

Samer
Mervilyne Pangan...
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 25 May 2009
Posts: 53
Dear Gentlemen,

Thanks for the info...

Im getting ready for a debate with Construction Manager.

Thanks,
Oliver Melling
User offline. Last seen 5 years 8 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
Normally a pre-defined table in the Tender documentation.

Best created at a higher level than tasks, as its purpose is to allow comparison of the price between contractors across certain activities/phases on the project.
Rodel Marasigan
User offline. Last seen 1 day 22 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Mervilyne,
My understanding with Activity Schedule under NEC3 is the Activities list with Lump sum price or Activity with Target Cost of LS price plus fee. More often it is presented on tabular or table form and a replacement of BOQ or Schedule of Rates.