1- during the tender stage ,all tenderer have to study the tender documents carfully and to familize them self with the actual site conditions by visiting the site and coordinating with the services authorities in order to gather all the required information.
if ther is any more clarifications the tendrers can send quary to the engineer to get the clear answer.
the engineer has to obtain No Objection Cetificate for the final design from all services autorties and the same has to be handed over to the contractor in the begaining of the project and it show the status of the existing utilites and the proposed utilities as well.
if the contractor after all this foung any utility obstructing the works and was not shown in any of the drwaings he can submt his calim for EOT.
The basis for the claim of unforeseeable is that you need to show that you did your part ahead of time (before excavation) and you took confirmation in written from the authority that there were no obsticles where you wanted to excavate.
On the other hand, the Errors in Drawings are dealt with like any other issue. This is a variation. You send a notice, and follow it up with the cost and time impact.
The basis for the claim of unforeseeable is that you need to show that you did your part ahead of time (before excavation) and you took confirmation in written from the authority that there were no obsticles where you wanted to excavate.
On the other hand, the Errors in Drawings are dealt with like any other issue. This is a variation. You send a notice, and follow it up with the cost and time impact.
You must show the Engineer evidence that you have taken all possible actions to ask about the under ground utilites. If you have done that, and you have proof from the responsbile authority that no subsurface utilities are present in the place you want to excavate, then the case can be considered "unforseeable". Otherwise, you can not claim under this clause.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dear Hady,
please note the following:-
1- during the tender stage ,all tenderer have to study the tender documents carfully and to familize them self with the actual site conditions by visiting the site and coordinating with the services authorities in order to gather all the required information.
if ther is any more clarifications the tendrers can send quary to the engineer to get the clear answer.
the engineer has to obtain No Objection Cetificate for the final design from all services autorties and the same has to be handed over to the contractor in the begaining of the project and it show the status of the existing utilites and the proposed utilities as well.
if the contractor after all this foung any utility obstructing the works and was not shown in any of the drwaings he can submt his calim for EOT.
The basis for the claim of unforeseeable is that you need to show that you did your part ahead of time (before excavation) and you took confirmation in written from the authority that there were no obsticles where you wanted to excavate.
On the other hand, the Errors in Drawings are dealt with like any other issue. This is a variation. You send a notice, and follow it up with the cost and time impact.
With kind regards,
Dear Hady,
The basis for the claim of unforeseeable is that you need to show that you did your part ahead of time (before excavation) and you took confirmation in written from the authority that there were no obsticles where you wanted to excavate.
On the other hand, the Errors in Drawings are dealt with like any other issue. This is a variation. You send a notice, and follow it up with the cost and time impact.
With kind regards,
Samer
Dear Samer,
Thank you for your response.
I am doing my best to prove the "unforeseenability" of the obstacles we are encountering.
However, my query was to inquire on how the Employer is to be held accountable for mistakes in information. C
Thank you very much for your advice.
Regards,
Hady
Dear Hady,
You must show the Engineer evidence that you have taken all possible actions to ask about the under ground utilites. If you have done that, and you have proof from the responsbile authority that no subsurface utilities are present in the place you want to excavate, then the case can be considered "unforseeable". Otherwise, you can not claim under this clause.
Good luck.
With kind regards,
Samer