Interim EOT Determination

2 replies [Last post]
Francis Moyalan, ...
User offline. Last seen 5 years 20 weeks ago. Offline
Joined: 12 Feb 2005
Posts: 105
Groups: None
Hi Guys,

Engineer makes an Interim Extension of Time Determination in a project which has got 30% of time to be elapsed.EOT determined is for 4 more months from the baseline completion.

In this context, does the contractor need to extend his Performance Guarantee till that time period? I sit same the case with Workmen Compensation Policy too?

Thanks in advance

Replies

Sajid Balma
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 8 Jun 2007
Posts: 151
Groups: None
I may be bit late to reply but, anyways.

Usually, the Performance Guarantee expiry may not necessarily on a specific date and may have been floating with the issuance of final taking over certificate plus the DLP. So, it may not need to be extended and eventually no extra cost for any extension. The wordings of the PG needs to be checked Carefully .

Same is not true with WC policy or any other insurance policies so, the question of extension is very much valid and cost of such extensions may be claimed in view of EoT.

Regards
Samer Zawaydeh
User offline. Last seen 5 years 30 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Francis,

The Performance Guarantee must be kept valid until the handing over of the works.

The cost of the extension can be decided based upon the EOT later on. The main idea is that the Contractor must keep it valid and then claim for the cost.

Kindly make sure that you read the conditions of contract carefully. If you are using a FIDIC contract, then PG is under clause (4/2).

With kind regards,

Samer