Defects Liability Period

4 replies [Last post]
Samer Zawaydeh
User offline. Last seen 6 years 11 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear All,

1. Can a Contractor declare a dispute during the Defects Liability Period?

2. Can the Engineer issue a variation during this period?

Thank you.

Samer

Replies

Samer Zawaydeh
User offline. Last seen 6 years 11 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Neil,

The case with the client was how to determine which budget to use. The Project Budget or the Operational Budget. In both cases, it would be done by the same Contractor.

The final invoice is made after the end of the Defect Liability Period, then the Contractor submit his "Discharge" notice as per clause 14/12.

Thank you for your kind input.

Best Regards,

Samer
Neil Tait
User offline. Last seen 13 years 10 weeks ago. Offline
Joined: 31 Jan 2001
Posts: 29
Groups: None
1. Disputes can be raised any time - specific contracts and post-contract agreements may questions their validity. Disputes for events that have occured during DLP raise an eyebrow as they potentially stem from mis-administration of the contract - see item 2.

2. Unless expressely stated in the contract, I do not believe a variation should be issued during the DLP period i.e. beyond the contract completion date. In reality it reamins an easy tool to ’instruct’ a bit of this and that beyond the completion date; however the contractor is well within his rights to refuse the work or re-rate it.
Samer Zawaydeh
User offline. Last seen 6 years 11 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Thank you Andrew,

Best,

Samer
Andrew Flowerdew
User offline. Last seen 3 years 26 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Samer,

1. Yes usually

2. Probably

It is often the case that you can not refer a dispute to arbitration until after completion, (or substantial completion), but pretty rare if your contract says you can not until after the Defects Liability Period.

It is the case that some contracts do not allow the Engineer to issue variations after completion but it is now more normal that the contract expressly states that he/she can.

Depends on what your contract says - as always.