Over time the programme will change due to things you didnt include that you should have, clients instructions to carry extra works and other unforeseen circumstances. You need to read the contract conditions at to what you have to do to get the program pass the client but a programme is a live document. Look at it this way, something changes and you don’t change the program. You might as well just throw it in the bin as the programme does not reflect what you are doing. Make the changes and tell the client what they are, its up for approval so all he can do is reject it. Work with him to get it approved if not you could go a long time without an approved programme and that isn’t good in anybody’s book.
Please clarify if we are discussing a programme that is pursuant to a clause in the contract (FIDIC Clause 14.1, for example) or a document which is specifically identified as a Contract Document and therefore prioritised in the Contract Documentation Clause of the Conditions of Contract (5.2?)
If the program is to be produced pursuant to Clause 14.1 then it IS NOT a Contract Programme, it does not require approval only Consent for Use.
In this case you can update the programme in tems of progress, logic and delay and submit it in line with the report specification.
Dont try to hash the programme though, only change the logic if it works, dont delete it because its in the way, youll suffer later in the project.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Over time the programme will change due to things you didnt include that you should have, clients instructions to carry extra works and other unforeseen circumstances. You need to read the contract conditions at to what you have to do to get the program pass the client but a programme is a live document. Look at it this way, something changes and you don’t change the program. You might as well just throw it in the bin as the programme does not reflect what you are doing. Make the changes and tell the client what they are, its up for approval so all he can do is reject it. Work with him to get it approved if not you could go a long time without an approved programme and that isn’t good in anybody’s book.
Vijay,
Please clarify if we are discussing a programme that is pursuant to a clause in the contract (FIDIC Clause 14.1, for example) or a document which is specifically identified as a Contract Document and therefore prioritised in the Contract Documentation Clause of the Conditions of Contract (5.2?)
If the program is to be produced pursuant to Clause 14.1 then it IS NOT a Contract Programme, it does not require approval only Consent for Use.
In this case you can update the programme in tems of progress, logic and delay and submit it in line with the report specification.
Dont try to hash the programme though, only change the logic if it works, dont delete it because its in the way, youll suffer later in the project.
D.
If its a contract programme you cant change any link without the Engineers approval.
But ofcourse in your monthly report you can modify it along with the comments on your changes.