Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Subbies Penalty

3 replies [Last post]
Raphael Adeyemi, ...
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 23 May 2007
Posts: 51
Dear Senior Coleaques,

I am at lost as to what is the correct application of FIDIC Clause 47 (1) by Main Contractor to Sub-Contractor. The frequent copies of Subbies contract agreement coming to my desk put the maximum penalty or LD to 10% of the Main Contract Value. I considered this unfair. What of a situation where the sub-contract value is less than 10% of the main contract.

I guess it should be back to back contract with the subbies penalty of LD to 10% of subbies contract value.

Is any one there having a contrary opinion? HELP ME OUT PLEASE

Replies

A D
User offline. Last seen 4 years 15 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
But then, what the brownbook states, "CONTRCAT / SUBCONTRACT MANAGEMENT USER GUIDE".

I have not referred this from long time. May be anybody from Contracts can elaborate further and I believe, it will be 10% of the contract value and not the main contract value.

Raphael Adeyemi, ...
User offline. Last seen 10 years 24 weeks ago. Offline
Joined: 23 May 2007
Posts: 51
Thank you Jaya, that is my thought too
J Venkatesh PMP P...
User offline. Last seen 11 years 42 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
I do with you...

10% should be on the respective sub contract value only, not on the Main contract...


Venkat