Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Delay Penalty for Milestones

No replies
Kannan CP
User offline. Last seen 19 weeks 24 min ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

Hi,

Is there any form of Contract specifically mentioning the Delay Penalty/LDs for not meeting a milestone. In FIDIC -Red Book, in my understanding it is not clearly linked with a milestone, but for the overall works completion.

Appreciate- expert's advices.

Regards

Kannan

Patrick Weaver
User offline. Last seen 5 days 5 hours ago. Offline
Joined: 18 Jan 2001
Posts: 383
Groups: None

Under Common Law, failing to make progress on a project is generally not a basis for the client establishing a claim for damages. LDs are a reasonable pre-estimate of the damage suffered by the client for the late delivery of a project.  However, if the milestone is a staged handover of part of the project, then LDs can certainly be applied. 

Example: 

Milestone 1 - complete piling under wharf.  LDs cannot be applied, the only work following on is the contractor completing the wharf deck.

Milestone 2 - Hand over container berth 1 for commissioning (project involves several berths). LDs can apply the handover allows the client to start work towards earning revenue. 

Civil Law is a bit different, it allows the partie to a contract to pre-set damages for failing to achieve a contractual objective.

For more on LDs see: https://mosaicprojects.com.au/PMKI-ITC-020.php#Process1