Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Sub-Surface Conditions

3 replies [Last post]
Bolisetti Jogiraju
User offline. Last seen 6 years 5 weeks ago. Offline
Joined: 7 Jul 2007
Posts: 32
Groups: None
Hi
Friends !

If the Employer has not obtained data on sub-surface conditions would it be practicable for a Contractor to carry out sub-surface investigation pre-tender ?

I welcome all your openions & suggestions.

Cheers

Replies

Bolisetti Jogiraju
User offline. Last seen 6 years 5 weeks ago. Offline
Joined: 7 Jul 2007
Posts: 32
Groups: None
Hi Raphael & Jaya

Thanks for your openions & views.

let us wait for some more views on this topic.

Thanks again

Cheers
J Venkatesh PMP P...
User offline. Last seen 12 years 4 days ago. Offline
Joined: 7 Aug 2006
Posts: 52
Groups: GPC Qatar
Normally,

During the Pre Tender stage (Especially for Buildings), no contractor will do a physical check by appointing an agency..(Since it is in tendering stage) They will check for the data from the near by ongoing / existing projects, if any...

Even if the client had given the data in the Tender document, am sure wisely they would add "Soil data given in the Tender is for information purpose only, contractor has to confirm/check the data before quoting"

Venkat
Raphael Adeyemi, ...
User offline. Last seen 10 years 35 weeks ago. Offline
Joined: 23 May 2007
Posts: 51
The Contractor has a duty to himself in ascertaining the sub-surface condition of a work he intends to carry out activities on. This normally is based on experience to avoid future arguement on whose shoulder the responsibility should there be a failure in future. Secondly the tender documents direct the tenderers to ascertain all factors that will enable him quote and execute for the work in other words sufficiency of tender.

I had worked on a bridge project for which the piling works were carried out obviously long time ago without adequate documentation. We insisted on a separate investigation to determine the structural stability of the existing works and our fear was confirmed as the pile loading test failed.