Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Celing Plaster above False Celing ( around walls also )

2 replies [Last post]
Puthenpurayil sug...
User offline. Last seen 17 years 23 weeks ago. Offline
Joined: 9 Oct 2006
Posts: 11
Groups: None
Dear Member,

One more quorry ... regarding the subject item..

If the False Celing is specified in Drawing/Specification is it necessarry to plaster the subject area ???

What is the difference between the terms of Structural celing/False celing..???

In a Lumsum Contract if it is not mentionened and the Client advise to delete the item in specified areas, is it applicable Contractually...???

In general is it necessary for doing the plaster in that area whether specifically needed false celing...?

Dear experts, please advise...!!!!

Regards.

P.Sugathan ( sugathan__pp@yahoo.com )

Replies

Hilal Itani
User offline. Last seen 10 years 10 weeks ago. Offline
Joined: 7 Aug 2005
Posts: 20
Groups: None
Dear all,

In a lump sum contract, the Contractor should during the biding stage requested information on this issue, if not indicated in the Specs and drawings.

In addition, should there is plaster above F.C., for which I believe there is not, I agree that the Employer has the right to omit part of the works. Nevertheless, the Employer may require time saving for deleting such item depending on the amount of works of the same


Hope that the above replies your querries.

regards
Faried Khan
User offline. Last seen 13 years 24 weeks ago. Offline
Joined: 11 May 2007
Posts: 41
Groups: None
Hi

Generally, in the areas where it is specified to have false ceiling, no need to have plaster for the ceiling above, only maybe 10 - 15 cm high along the wall cornice above the false ceiling level only for the appearance, but in rare cases it might be specified otherwise.

I guess I don’t have standard description for both kind of ceilings, but by definition I understand, the Structural ceiling has a structural function such as carrying dead and live loads of the structure, and the false ceiling it has mainly Architectural function.

I don’t understand, how it is not mentioned and the Contractor insists to carryout plaster for the ceiling and walls above the False ceiling level!!, anyhow in any case the Client would have the right to instruct omission of such plaster and the respective unit rate would be revised accordingly.

Anybody would have opposite opinion?

Thanks