Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

SUBSTANTIATE DOCUMENTS FOR CLAIMING

3 replies [Last post]
jack smith
User offline. Last seen 18 years 32 weeks ago. Offline
Joined: 16 Mar 2006
Posts: 8
Groups: None
HI GUYS,

Anybody have any ideas, under FIDIC "Condition of Contract for Plant and Design-Build for electrical and mechanical works and for building and engineering works designed by the Contractor" First Edition 1999 ........

Where Engineer insturction being issued out appointing xxx consultant as domestic consultant with an agreed price of USD xxxx.xx , and confimed 3% attendance which is issued in accordance with Clause 3.3 of the contract .

Question :

1) Is it necessary to substantiate documents when submitting progress claim for the appointed consultant ??

2) Amount allocated inside the Engineer Instruction , is it subject to changes

Extra ....
A) Sub Contractor for tiling work being appointed as nominated.

B) Tiles supplier being nominated.

C) Our position now is as a Main Contractor. Client required 3% spare materials to be on site upon handover.

Question,
- Estimated Quantity of tiles to be come from Main COntractor or Nominated Tiler.

- If quantity order being more that 3% , and client won’t accept more than 3% who should bear the cost ????

Replies

Ranilo Asiao
User offline. Last seen 12 years 11 weeks ago. Offline
Joined: 7 May 2004
Posts: 11
Groups: None
HI,

Where Engineer insturction being issued out appointing xxx consultant as domestic consultant with an agreed price of USD xxxx.xx , and confimed 3% attendance which is issued in accordance with Clause 3.3 of the contract .

Question :

1) Is it necessary to substantiate documents when submitting progress claim for the appointed consultant ??
The price is not necessary because as you said it is already an agreed price, but you need to substantiate the quantity installed or progress of the work.

2) Amount allocated inside the Engineer Instruction , is it subject to changes?
It depends on what is your reason, but if you had already agreed before then it is very difficult to change position without valid reasons.

Extra ....
A) Sub Contractor for tiling work being appointed as nominated.

B) Tiles supplier being nominated.

C) Our position now is as a Main Contractor. Client required 3% spare materials to be on site upon handover.

Question,
- Estimated Quantity of tiles to be come from Main COntractor or Nominated Tiler.
Both, because you are paid 3% attendance as paid for close coordination for the nominated sub-contractor.

- If quantity order being more that 3% , and client won’t accept more than 3% who should bear the cost ????
The source of quantity. As a main contractor, you are responsible to closely coordinate all the works inside of your scope of work including nominated works.
I had assume that you are paid by the owner then you will pay the nominated sub-contractor means you are paying directly the nominated sub-contractors not they are directly paid by the owner. If my assumption is wrong then just make it the opposite.

hope you understand my explanation.
Shahzad Munawar
User offline. Last seen 9 years 29 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
Mostly it is contractual requirement and also it is essential that you substantiate your progress to the Consultants /Client with proper documentation.
Charleston-Joseph...
User offline. Last seen 3 years 17 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hello Jack,

What are you doing there in Vietnam? Is it a nice place to work?

My answer to your question no.1: Yes, it is very important to substantiate your progress billing to the client. This is the norm worldwide.

Cheers,

Charlie