Hi All,
The following has been giving sleepless nights for a long time. The situation is like this -
1. UB Slab Target Completion - May 26, 2004
2. UB Slab Actual Completion - June 10, 2004
3. UB Columns Taget Completion - June 6, 2004
4. UB Columns Actual Completion - June 15, 2004
5. GF Slab Target Completion - June 13, 2004
*(Now is the hitch)
6. Consultant instruction to reduce slab levels in periphery - June 20, 2004.
7. GF Slab Actual Start - July 4, 2004 (after redesigning of slab)
At the time of issue of revised slab levels the project was showing a delay of 17 days. A claim was raised for EOT but, turned down by the consultant as the they claimed that the instruction was not in the way of the natural progress of works as the delay was already 17 days.
How do I claim for EOT now? ANd, what would be the substantiated claim?
Vishwas
Replies