Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Provisional sums and baseline schedules

7 replies [Last post]
Dinesh Kumar Dama...
User offline. Last seen 8 years 45 weeks ago. Offline
Joined: 24 Feb 2002
Posts: 68
Hi everyone,

Do you usually include provisional sums in your baseline schedules or not and why

Regards

Dinesh

Replies

David Barry
User offline. Last seen 18 years 22 weeks ago. Offline
Joined: 7 Jan 2003
Posts: 27
Groups: None
David’s view is the correct one IMHO, particularly where the contract invokes the standard method of measurement.

This clearly indicates that the contractor is not entitled to time for the expenditure of defined provisional sums whereas he is entitled to time for the expenditure of undefined provisional sums. It follows therefore that he must include within his programme for the defined provisional sum, and should not include for undefined provisional sums.

If contract is silent re SMM or time for provisional sums, I suspect it is still wise to follow these gudielines as it probably represents industry standard - do people agree with this suggested policy?

Obviously if the contract is specific as to how time for provisional sums is dealt with then that must govern.

Regards
David
Stuart Ness
User offline. Last seen 12 years 46 weeks ago. Offline
Joined: 30 Jun 2004
Posts: 352
Groups: None
I would agree with David; the Baseline Schedule should take account of the reasonable time expected for carrying out work under a Provisional Sum if the PS is defined. If the PS is not – or cannot be - defined, then I think that although it may not be necessary to take account of the PS, it would nevertheless be advisable to make some provision for it in the Baseline Schedule (no pun intended!!).

In either event, whether the scheduling provision is excluded entirely or only shown provisionally, I would suggest that the Baseline Schedule is qualified with a note clearly stating that the time required to execute and complete the work related to the PS is itself provisional and cannot be confirmed until instructions (and the timing thereof!!) are issued in regard to the PS.

Stuart

www.rosmartin.com
David Bordoli
User offline. Last seen 8 years 31 weeks ago. Offline
Joined: 8 Apr 2002
Posts: 416
Hi all

I beleive there is a requirement to take account of ’defined’ provisional sums in the baseline programme. It’s only ’undefined’ sum that you can wait until they are expended.

David
Ian Scrimshaw
User offline. Last seen 13 years 16 weeks ago. Offline
Joined: 5 Jun 2001
Posts: 6
Groups: None
Hi guys,

I think that I am in agreement with you both, that it is not appropriate for a Contractor to include activities relating to provisional sums in the baseline schedule.

I can think of one project where the inclusion of a number of activities relating to provisional sums in the baseline schedule has worked against interests of the Contractor.

I think that it would be better to wait until the provisional sum item is instructed and then to produce a revision to the baseline schedule

Regards,

Ian
Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
Depends on whether you are client or contractor. A provisional sum should be in the clients baseline, the difficulty is that you dont know if/when the money will be spent, so you would have to agree some method of distribution. The contractors plan should definately not include provisional sums.

HTH
Dinesh Kumar Dama...
User offline. Last seen 8 years 45 weeks ago. Offline
Joined: 24 Feb 2002
Posts: 68
Hi Steven,

Thank you for your reply.

I agree with you, actually I was asking about the baseline schedule in relation to provisional sums.

Thanks & regards

Dinesh
Steven Oliver
User offline. Last seen 12 years 1 week ago. Offline
Joined: 8 Nov 2002
Posts: 313
Groups: None
IMHO, a provisional sum is a pot of money set aside by the client which may or may not be expended.

Therefore a contractors contract price should exclude all such sums, as the contractor does not know whether the money will be spent, let alone when.

HTH