Inclement Weather EOT

11 replies [Last post]
Nestor Principe
User offline. Last seen 20 years 50 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 19
Groups: None
Dear All,

Hope this case will attract the attention of everybody to share their won opinion.

Say...

The contract allows EOT due to inclement weather on condition that no prolongation cost will be paid. If an EOT is granted and within the said extension an inclement weather has occured, would the contractor be entitled to prolongation cost for the inclement weather delay within the EOT period. I would like to look at it as similar to incidental Sundays and holidays where prolongation cost is being paid.

Thanks to your opinion.

Regards,

Nestor

Replies

Geoffrey Boulton
User offline. Last seen 6 years 13 weeks ago. Offline
Joined: 27 May 2004
Posts: 21
Andrews reply has good merit. given that HK (I asume that is where the work is taking pace) has a definite typhoon season it would only be reasonable to expect reimbursement of costs if the client delays have pushed you into that time of year.

Definitely worth looking at from that prospective.
Charleston-Joseph...
User offline. Last seen 3 years 30 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hi Nestor,

Andrew idea is another smart move on your part if ever you will find one.

Cheers
Andrew Flowerdew
User offline. Last seen 3 years 14 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
All,

See adverse thread - Weather - Employer or contractor risk

Tou will not be entitled to any money for the eot but you might be entitled to money if the client delays have caused you to do work in a period of adverse weather that if the delays had not occurred you would not have been working in.

Shahzad Munawar
User offline. Last seen 9 years 42 weeks ago. Offline
Joined: 2 Jul 2003
Posts: 551
Groups: None
It is evident that you are only entitled for EOT not any cost due to Inclement weather condition as per your Contract.

You may cover this event under any other item for which you may get pronlogsation costs.
Charleston-Joseph...
User offline. Last seen 3 years 30 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Hi Nestor,

It is very clear that EOT due to inclement weather has no prolongation cost. As you have stated, a precedent was already established (one month extension due to inclement weather without prolongation cost). In the case of 15 days EOT due to inclement weather, there will be no prolongation cost.

You play smart, look for event that may will cause EOT with prolongation cost during the 15 days extension of time (w/out cost). This is the only way you will be able to recover cost and minimize your losses.

cheers
Nicos Pozatos
User offline. Last seen 2 years 27 weeks ago. Offline
Joined: 27 Jun 2001
Posts: 25
Groups: None
Dear Nestor,

I have exactly the same case like yours. That is Inclement Weather during the extended performance period. I have started a new topic and then I saw your topic. If you have time read under topic "Adverse Weather - Employer or Contractor Risk " and give me your opinion and/or what was the outcome in your case.

Nestor Principe
User offline. Last seen 20 years 50 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 19
Groups: None
G.Rayco,

Thanks to your reply. Certainly, the reference you gave will help a lot.

regards,

Nestor
Forum Guest
User offline. Last seen 30 weeks 3 days ago. Offline
Joined: 28 Jan 2009
Posts: 2
Groups: None
Dear Nestor,
If, During the extension period (01 April 2003 to 30 June 2003)Progress has been delayed as a result of an excusable and compensable event (cause by the client),Contractor may then become entitled to compensation for the effect of inclement weather as a result of lost productivity during inclement weather.

Ref: Delay and Disruption in construction contracts,Keith Pickavance,2nd edition,page 394,para. 11.33 and 11.34

Hope this can assist u."Kabayan"

G.Rayco
(2598)
Nestor Principe
User offline. Last seen 20 years 50 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 19
Groups: None
Dear Ronald and Se,

Thanks to your reply.

I would like to give a very typical example.

A two year contract was scheduled to be completed, say, 31 Mar 2003. The contractor was granted two month EOT due to variations and one month EOT due to inclement weather or a total of three months EOT. Thus the revised completion was 30 June 2003. During the extension period (01 April 2003 to 30 June 2003) there were 15 days inclement weather that has occured extending the completion date to 15 July 2003.

Would the contractor be entitled for prolongation cost from 01 July 2003 to 15 July 2003?

The contract was very specific. EOT is allowed for inclement weather however, no prolongation cost will be paid for EOT due to inclement weather.

The contractor have received prolongation costs for the two months EOT due to variations. There was no prolongation cost paid for the one month EOT due to inclement weather during the contract period.

I hope I make the case clear to you guys.

Regards,

Nestor
Ronald Winter
User offline. Last seen 3 years 49 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
Perhaps you need to step back and look at your problem again. Ask yourself, “Why would the Owner pay for your overhead (prolongation) costs should the project be extended due to weather?” Is the Owner responsible for the weather (and thus, the costs incurred?)

If the Owner were responsible for the weather, then you would have a reason to expect them to compensate you for the unexpected cost. Otherwise, we consider this a case of ‘force majeure’, where the time would be excusable but non-compensable.
Se de Leon
User offline. Last seen 3 years 28 weeks ago. Offline
Joined: 15 May 2001
Posts: 321
Groups: None
Hi Nestor,

It will depend really on what the contract says. I had the same problem 4 months ago wherein our client uses a form of contract that is clear on extension of time but silent on compensation for EOT. They acknowledge that there is an obvious expense on our part, but the problem is where to find a basis if the contract is silent. We have used the principle of quantum maruit but to no avail.

Hope this will help.

Regards,

Se