I have seen several contract specifications which state that a contractor must anticipate x amount days of inclement weather delays into their baseline schedule. For instance, one project that I am currently working on states that the contractor should anticipate 24 inclement weather delays for every 12-month period. Further, it states that a lost workday occurs when more than one half of the scheduled hours are lost as a result of inclement weather. Once the 24 inclement weather delay days have been overrun, excusable delays would be considered provided that the work affected by weather is on the critical path.
The issue here is, do we have the contractor build in non-work periods into the P3 calendar? If so, then what do we do once we pass the planned weather delay days during the update period? Roll them forward? If you continue this way until the end of the 12-month with no weather delays then can the contractor say I’ll take off for a month?
On most of the projects with this verbiage, I have been trying to get the contractor to note the activities that are most likely to be affected by weather during the development of the baseline but not build in crystal ball type dates into the P3 calendar. Rather, I keep an updated spreadsheet and keep tabs or when we mutually agree that an inclement weather delay has been realized during the monthly update cycle.
Anybody have any experience here or suggestions?
Sincerely,
Peter Malvese
pmalvese@mta-esa.org
Replies