Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

4D Planning for Turnarounds and Shutdowns

3 replies [Last post]
Eckart Schenck
User offline. Last seen 4 years 39 weeks ago. Offline
Joined: 25 May 2005
Posts: 28
Groups: None

Hi there,

I am looking for details on 4D planning/BIM and progress control used for turnarounds (e.g. for refineries or processing plants). Those schedules are very detailed and big, often with many hundred pieces of equipement, piping etc. and thousands of activities.

Can anyone share experience about this toppic?

Or are there any case studies available?

 

Thank you all!

Replies

Jaishankar Pandey
User offline. Last seen 23 weeks 4 days ago. Offline

Hello Eckart

 

I am working for integration of schedule with model project.

 

Is it possible for you to share thee tool you have mentioned in your reply. 

 

Thank you

Eckart Schenck
User offline. Last seen 4 years 39 weeks ago. Offline
Joined: 25 May 2005
Posts: 28
Groups: None

Hi Jaishankar,

 

thank for your message.

We have experimented with Navisworks Manage, which works fine for projects where a complete 3D model is available.

For shutdowns we have the challenge that there is no consistent model of the complete plant, because most parts of it are very old.

To work around that we have now developed our own tool which only needs some basic equipment data (like equipment type, tag no., x/y/z - coordinates and progress data). The tool imports the data into AutoCAD and creates automatically a 3D model with generic symbols for each of the equipment types. The result is a simple 3D model with filter options for equipment as planned / delayed /critically delayed / completed.

cheers!

5915
terminplan3d_01.png

Jaishankar Pandey
User offline. Last seen 23 weeks 4 days ago. Offline

Hello Eckart

You may use Naviswork Manage timeliner application to link your detailed schedule activities with the 3D model. 

You need to check the unique code of equipments / items from model and modify the corresponding activity description in your schedule accordingly.

Then you can import the Schedule in naviswork manage timeliner. This will allow you to link time with 3D model and that will result in 4D. You can use simulation to see the construction progress against time period.

Thank you