Column Heading Shading / Font Colour Change

1 reply [Last post]
Taner Aysel
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 15 Apr 2019
Posts: 2
Groups: None

Hi All, 

 I would like to change column heading row shading / background colour to light grey when I am printing out programme in ASTA powerproject, 

 Does anyone know how to do it?

Your help would be really appreciated, 

 Regards

Taner

Replies

Barry Casey
User offline. Last seen 2 years 31 weeks ago. Offline
Joined: 25 Jun 2019
Posts: 5
Groups: None

Format Tab > Hierarchy Appearance > Choose colour