Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

As Planned Vs As built - Comparison

1 reply [Last post]
Dominic Planner
User offline. Last seen 1 year 3 weeks ago. Offline
Joined: 7 Jun 2017
Posts: 22
Groups: None

Good morning, 

I am looking to compare the as built with the as planned - Is it possible to export this in some format into excel to compare variances in duarations? Or is there an easy way to compare i.e. Planned 5 days, As built 10 days?

Thanks in advance, 

Dominic 

Replies

Yasine Ali
User offline. Last seen 5 years 3 days ago. Offline
Joined: 12 Aug 2015
Posts: 18
Groups: None

You could baseline your as planned programme and then insert this in your as built programme.

Then format the chart to show the baseline on its own line which will show you the difference in durations.