Vladimir,
I want to keep my Contract Schedule separate from SPDM versions for Optimistic, Probable and Pessimistic as Probable is not equal to Contract Plan. I also want to keep another separate Schedule for whatever, perhaps Plan B and “what if”, in this last version I will add my switches and will toggle on and of relationships at will, will be my punching bag but I don’t want to duplicate the effort on updating several versions by entering actual data once more as it is time consuming and error prone.
I remember reading one of the tables related to performance updating cannot be exported, perhaps monitoring table, and this blocked my mind about exporting performance archive, functionality now I believe will allow me to do what I am looking for.
In order to better understand this functionality I ask you, does import performance archive data from another project overrides actual values on the second?
Best regards,
Rafael