Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Turnaround & Shutdown (T/A & S/D)

DEFINITION

Turnaround is a planned shutdown of any plant where a large number of activities, in terms of various of discipline have to be executed in a specified / predefined duration. The major challenges in this activity lie with completing the activities and restore the Reliability and Integrity of the facility within the defined premises of duration as per the Corporate Business Plan.

Turnaround entails an extensive seamless planning, resource mobilization and optimization to make it successful in this resourced scarce environment. Typically the planning takes 12 to 18 months for an execution ranging around 2 to 4 weeks hence the whole lifecycle should be considered as a project from its inception to realization. During Turnaround execution the proper monitoring of the whole jobs / activities is required to avoid any delay / slippage from the execution plan.

Comments

Free Webinars on Turnaround / Shutdown (Progressing using P6)

Emerald’s Turnaround Progressing System (TAPS) uses barcode scanning technology to make updating Oracle Primavera P6 schedules a breeze.

Turnarounds, shutdowns and outages (TSOs) are high-profile, complex and time sensitive projects. With millions of dollars on the line each day in lost revenue and labor costs, it is critical that the TSOs be completed on schedule.

Emerald’s Turnaround Progressing System (TAPS) uses barcode scanning technology to eliminate the need for lengthy manual data entry when updating your Oracle Primavera P6 schedules. Simply use a barcode scanner to find, start and update any activity within the schedule in two fast scans.

TAPS increases your accuracy and cuts your shift statusing time by 75%. Shift reports are delivered on time, allowing management to make informed decisions based on timely insight into the current health of the TSO. Less experienced, less expensive resources can take on the job of updating tasks, while experienced schedulers are freed to analyze and act on the latest data. As a result, issues are avoided or mitigated before ballooning in to larger more expensive problems and the TSO remains on schedule.

Join our free webinar and see how easy TAPS is!
  
https://lnkd.in/g9F3BhY

We have published extensive

We have published extensive essays on turnaround planning and management:

Essay on Management methodology:  http://www.interplansystems.com/pmbok-turnaround-management/

Management Primer:  http://www.interplansystems.com/turnaround-project-management-primer/

Planning Primer:  http://www.interplansystems.com/turnaround-project-planning-primer/

List of services required during a typical Turnaround

Dear Mufiz, Your posts are on my tracking list and I found your posts extremely helpful. I wonder if you can post list of services required during a typical petro-chemical turnaround. I will greatly appreciate your help. Regards

Turnaround Key Success Factors:

T/A success indicators, as shown in table below, is established in order to have a common measuring tool for all to enable for future T/A benchmark and improvements.

 

 

SL NO.

CRITICAL FACTORS

WEIGHT

DEFENITION OF WEIGHT

1

Estimated Hours

5

“T/A SOFTWARE” estimated Hours Vs. Actual Mainframe System inputted hours. (+/- 5%)

= 5 Points Earned.

Every 2% differential from 5% = Minus 1 Point

2

Health & Safety

15

0 / LTA = 0 / OSHA = 15

1 / LTA = Minus 5

1 / Recordable First Aid = Minus 2

2 / LTA = 0 Point Earned

3 / RFA = 0 Point Earned

3

Personal Exposure

10

0 Reportable = 10 Points

Each Reportable = Minus 2 Points

4

PSSR Effectiveness

5

0 Violations = 5 Points

Each Violation = Minus 1 Point

5

Environmental

10

0 / Reportable = 10 Points

Each Reportable = Minus 3 Points

6

Schedule Attained

10

“T/A SOFTWARE”Shift Schedule and Estimated Hrs. Vs. Actual Shift Hours and Mainframe Sys. Inputted Hrs.

Planned Shift Schedule (+/- 5%) differential = 5 Points

Percentage differential from estimated to actual

= Percentage of points earned.

Actual Shift hours to planned (+/- 5%) differential

= 5 Points.

Percentage differential from estimated to actual

= Percentage of points earned

7

Work Scope Completed

5

Final approved work list Vs. Actual Work done during outage.

100% of work list completed = 5 Points.

 

Deletion of work list items due to time or manpower constraint not effected by additional work identified during the outage equals to percentage of work lists items to total work list = the same percentage reduced from the weight.

8

Quality Goals

10

0 / Start up delay = 10 Points

Each Flange Leak = Minus 2 Points

9

Productivity

10

As measured by fieldwork sampling and

Schedule Vs. Actual.

80% Productivity and above = 10 Points

70% / 80% = 8 Points

60% / 70% = 6 Points

50% / 60% = 4 Points

Anything below 50% = 0 Points earned

10

Cost within Estimate

5

Estimated Cost Vs. Actual Cost.

(+/- 5%) = 10 Points earned.

Every 1% differential from 5% = Minus 1 Point

11

Cost within Budget

5

Budgeted Cost Vs. Actual Cost.

(+/- 5%) = 5 Points earned.

Every 1% differential from 5% = Minus 1 Point

12

Planning Accuracy

10

All planning accuracy is weighted against original approved work scope.

 

Actual Shift Schedule Vs. Planned Shift Schedule

0 Differential = 5 Points.

Percentage differential from Estimated to Actual = Percentage of points earned.

 

Actual Manpower Vs. Planned Manpower

0 Differential = 5 Points

Percentage differential from estimated to Actual Percentage of points earned.

 

 

 

Turnaround Scope Challenges

Project Guidelines

• Ensure project scope is reviewed to identify & include tie-in only in the T/A scope

• Agree on cut-off date for projects to be issued to T/A planning team

• All T/A projects scope to be integrated with the T/A scope

• Consider only projects with FEEP.

Turnaround Scope Challenges

Additional Job Approval

The following criteria need to be applied for any additional job after job list freezing :

• Is justification accepted and work require S/D to implement?

• Is work required to meet desired long run, plant integrity/availability?

• Is work required to maintain SH&E performance?

• Have alternative (on-stream work) methods been considered?

• Will all material be available on site as per the milestones date?

• Will final work package/schedule be completed as per milestones date?

• Is there alternative funding available (not from T/A budget)?

Turnaround Scope Challenges

Scope Challenge Team

 

• Concerned Operation Specialist, Supervisor or Engineer

• Concerned Engineers (Inspection, Process, Mechanical, Electrical and Instrument)

• Concerned Maintenance Supervisors, Engineer or Specialist

• Planning Team Lead

• Area Planners

• Area Manufacturing Facilitators (2)

Turnaround Scope Challenges

Expected Outcome

• Frozen integrated T/A job list

• T/A cost estimate

• Tentative T/A milestones

• Optimum T/A duration

• Work list dropped items

• Improvements achieved (cost, duration, volume, etc.)

• Final report with recommendation

Turnaround Scope Challenges

Scope Challenge Steps

• Forming Review team

• Determine the review date

• Arrange the introductory meeting with affiliate management

• Conduct the review

  - Review T/A premises and ensure all requirements are explained well     - Validate every item in the scope against the criteria     - Assess every item in the scope against MeridiumRisk Matrix     - Benchmark the estimated duration with the nest in class (within SABIC or Others).     - Ensure the good balance between Risk & Cost factors

Turnaround Scope Challenges

Objectives

 1. Focus on the delivery of value adding jobs

2. Reduce the T/A cost

3. Reduce the T/A duration

4. Ensure the proper alignment & commitment on the final scope

5. Freeze the work list

6. Ensure effective addition work approval mechanism in place

 

 “The above need to be completed in an open and professional manner in order to maximize profit by ensuring minimum T/A cost, but at the same time no compromising on safety, health, environment, integrity, reliability, and subsequent availability of the plant & equipment.”     T/A Scope Validation Criteria   1. Is this job included in the T/A to establish or validate MI? 2. Is this job included to meet legislative requirements? 3. Is it to restore the operability of the plant? 4. Is it to restore the reliability of the plant? 5. Is it to restore the efficiency of the plant? 6. Does it provide data/information which help in reducing the work volume in the future? 7. Does it provide data/information which help in extending the inspection/maintenance intervals? 8. Could this job be executed outside T/A?  

T/A INFO...

SALAM  MUFIZ SAYEED..

 

thank you for the information provided.........

 

great job keep up the good work..

 

 

BEST REGARDS,

 

IMRAN.

Turnaround & Shutdown (T/A & S/D)

Turnaround EXECUTION Phases

1. Pre-Shutdown before the Turnaround

  1. Fabrication overall list
  2. Scaffolding needed, location & quantity
  3. Painting job needed for the time can be done only during the shutdown
  4. Post shutdown activities from previous
  5. Logistic section for heaving lift, pick-up, sedan car, drinking water, house keeping
  6. Project or Capital Items for replacement or tie-in
  7. Overtime cost charge during the Shutdown period

After above Lists and group assigned finished. Each section head or Planner has to work out material bill list, service requirement, and overall material cost taking from Warehouse Stock. Then find the overall estimate cost to each line items and adding with 15% to the final total cost as  for Turnaround Budget

This has to be done 12 months before the Turnaround

Turnaround & Shutdown (T/A & S/D)

Turnaround Time and Duration Setting

At our company SABIC, T/A is 4 Years Cycle for every individual processing plant, duration has to be considered as below:

  1. Business Objective Plan and Market demand
  2. Asset Management replacement Plan for Capital Budget
  3. Process Catalysts performance and life band
  4. Bad Actor showing up after start-up from previous turnaround
  5. Project installation and Tie-in time base on Fabricator and Contractor Plan
  6. Rotating Equipment Overhauling time

With above line items we can find the best starting date and find the longest duration to fit for item #2,#3,#4,#5 or #6 as the duration. But add 5 days time more for Operation as regular size, and add 8 days more for Operation if there is Catalyst require for reduction process before going on service.

Turnaround & Shutdown (T/A & S/D)

Work list

When a Turnaround/Shutdown is declared the planning group should develop a full list of the existing work as a basis for the "Turnaround/Shutdown Work List".

Additions to the work list should be requested from Operations and Maintenance Groups.

A definition of acceptable Turnaround/Shutdown Work should be issued and all additions must be screened against the definition to ensure that the Work meets the criteria.

Turnaround work is defined as:

  • All jobs that are necessary for continued operation and can only be done safely at the time of a plant Shutdown.
  • Planned maintenance tasks that can only be safely accomplished at the time of a plant shutdown.
  • Statutory Inspection requirements for the next 5 years.
  • Any Job necessary for continued operation that could be undertaken with the plant running but pose a significant risk of causing a plant disruption.
  • Project construction works that needs to be executed during Plant shutdown (E.g.: Tie-in jobs)

Turnaround & Shutdown (T/A & S/D)

Plan for the Plan (Milestone Plan)

The Plan for the Plan is a device used to layout milestone and then monitors the progress of all the elements of Turnaround/Shutdown preparation.

A simple low-level plan is created with an activity for all the elements required to create a Turnaround/Shutdown  plan along with all other elements of Turnaround preparation.

These include:

  • Scope of Work
  • Supporting documents
  • Communications
  • Contingency Planning
  • Contract management
  • Cost control
  • Management Philosophy
  • Manpower recruitment
  • Material Procurement
  • Planning Progress
  • Operations interface
  • Project development
  • Risk Management
  • Specialist Contractors
  • Work list control

Periodic Turnaround/Shutdown  Calendars will be issued, extracted out of the 'Plan for the Plan' to focus on activities due for the coming 2 months. The Turnaround/Shutdown  calendar to be updated according to the needs.

Turnaround & Shutdown (T/A & S/D)

Planning Team

A planning team should be formed early in the Turnaround/Shutdown process (normally 18 months before the event) after announcing the Turnaround Manager. The team should be under the control of a Turnaround Planning Leader and should consist of the following:

  • Mechanical Planners for all Static Equipment
  • Mechanical Planners for all Rotating Equipment
  • Instrument Planners
  • Electrical Planners
  • Process Representative
  • Operations Planners
  • Inspection Engineer
  • Civil/Structural/Painting
  • Materials Planners
  • Cost Engineer
  • Planning Administrators

The team should be sized to ensure the all aspects of the plan and cost estimation can be completed and reviewed in time for test prior to the Turnaround/Shutdown.

Additional Planning support team members should be nominated from each Department / Sections for single point contacts channeling Turnaround/Shutdown related information to the respective sections, represent the Section in Turnaround/Shutdown related meetings and easy resolving of Turnaround/Shutdown related issues.

Turnaround & Shutdown (T/A & S/D)

Indicators of concerns

The following list of "leading indicators" are a good predictor of Turnaround/Shutdown performance – if any of these appear, there is a high likelihood that one or more of the Turnaround/Shutdown objectives will not be met.

  • Key positions not assigned and not working full-time early enough to allow proper front-end loading of planning and preparation
  • Misalignment of functional milestone plans (between the different functions)
  • Work list not restricted per the milestone timing
  • Capital projects not appropriated per the milestone timing
  • Budget & corporate plan misalignment causes many recycles, diverting resources form detailed planning work
  • Late assignment of operations/ process resources to planning & preparation efforts
  • Issued-for-construction drawings not ready per the milestone timing
  • Major execution contractor(s) not in place per the milestone timing
  • Key personnel turnover
  • Shutdown and start-up plans and schedules not integrated with the maintenance / project work

Turnaround & Shutdown (T/A & S/D)

Keys to the successful implementation of Plan

  • All activities related to the Turnaround & Shutdown that require resources are input to the planning and scheduling system to enable effective resource scheduling.
  • All work activities are planned. The level of detailed planning and the amount of job preparation vary depending on the job. The level of planning must be value-added.
  • All personnel - Management, Maintenance, Operations/Process and all other disciplines or functions - are committed to planning and scheduling to enable efficient execution and to minimize lost production opportunity, that is, minimize the event duration.
  • A high-discipline level to execute agreed upon plans and schedules with high compliance exist throughout the organization.
  • Management input primarily through focus on providing guidance to the event planning & execution team, and by ensuring adherence to sound shutdown / turnaround planning & execution standards and practices.

Turnaround & Shutdown (T/A & S/D)

PLANNING PRINCIPLES

The function of the planning group in a Turnaround is to identify & locate all aspect of necessary items and prepare all aspects of the work to be executed so that the activity is executed safely at the shortest practical duration and lowest possible cost without affecting quality.

A fully integrated plan is essential for efficient Turnaround Control. This means a detailed Operations Shutdown and Start-up plan, linked to detail Mechanical and project plans to form one cohesive network including Pre-work, of-spec product to on-spec duration and work that can be completed outside of the Turnaround window.

The Plan when complete and reviewed should drive the work using task criticality, rather than monitor progress, (the plan should be pro-active not reactive)

Market Place

No results found... (try selecting a different content filter)