/ Construction Project Planner / Senior Planner, Larsen & Toubro (L & T) Limited, 000ft2 Office Building

START Date: 
July, 2012
END Date: 
October, 2013
  • Project management & cost control process, responsible for progress planning & monitoring.
  • Provides written updates on critical paths, schedule variances, progress and significant developments for inclusion in both Monthly and Quarterly Reports.
  • Evaluates the impact of changes on cost, schedule, operations and scope documents.
  • Participate in meetings with Project Managers and provide schedule related input.
  • Prepared & developed L2 & 3 Level Baseline construction programme in P6.2 & updating the same on weekly basis.
  • Record and
Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500

#planning #seniorplanner #planningengineer #construction #build #majorprojects, Al Turki Enterprises - Oman, Ras Al Hamra Development Project

START Date: 
October, 2013
END Date: 
June, 2014
  • Preparation, submission & obtaining approval for fully resource & cost loaded schedule using Primavera P6.7
  • Core team member for implementation of SAP – PS module for project planning & tracking.
  • Preparation of daily, weekly & monthly reports in strict compliance with procedure implemented by Halcrow ME as a part of project controls process.
  • Played an important role in developing & implementation of salary structure for manpower based on productivity delivered.
  • Productivity analysis.
  • Preparing two/four week look ahead.
Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
250
Experience Hours (Forensic Analysis): 
250

#planning #seniorplanner #planningengineer #construction #build #majorprojects, Urbacon Contracting & Trading, VVIP Palace & Qatar special projects division

START Date: 
June, 2014
END Date: 
January, 2016
  • Preparation of fully resource and expense loaded Baseline Construction programme in Primavera R8.2.
  • Updating and progress tracking of Baseline schedule, report preparation including for Monthly progress reviews includes preparation of S-curves (Physical), progress summary, Look ahead plan, productivity reports.
  • Preparation of KPI dashboards for progress measurement.
  • Formation on EPC related SPIs and S-curves and forecasting the risks.
  • Preparation of Delay tables, Productivity reports for all skilled categories for performance monitoring and to ensure rig
Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500

/ Construction Project Planner / Senior Planner / Forensic Analyst, Al Futtaim Carillion, Madinat Jumeirah, Thematic districts EXPO 2020

START Date: 
January, 2016
END Date: 
August, 2018
  • Preparation of fully resource loaded baseline programme for AED 2.21 Billion EXPO 2020 Thematic districts project & getting approval from PMC Ch2mMace.
  • Established programs with PMT (Project Management Team) taking design and engineering, civil and MEP works, subcontractors and other work activities into account. Close coordination with these disciplines in order to have feasible project program available.
  • Tracking and monitoring all project activities on regular (weekly) basis.
Experience Hours (Planning & Scheduling): 
3500
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
1000

Senior M&P Planner, Balfour Beatty Construction Services UK, TMF Project - Urenco Capenhurst

START Date: 
July, 2015
END Date: 
November, 2016
This is Balfour Beatty Major Constructions first integrated project combining their Electrical division and their Mechanical Bromborough office. Additional to the development of the M&P scope with the integration of the E&I scope was the alignment of supervision to the benefits of timely and accurate reporting allowing them to arrange their resources more efficiently. Due to ongoing scheduling access issues with other contractors, engineering and material shortages the project was re-baselining twice.

Susan Yates

First Name: 
Susan
Last Name: 
Yates

I have over 13 years’ experience working as a project planner in both client and contractor organisations working on multi disciplinary rail projects.

I also worked for  4 years as a Signalling Designer achieving and maintaining an IRSE Signalling Designer licence

Professional Since: 
Jun-2005 (19.8 yrs experience)
Years Experience: 
0

CH2M, Senior Planner Client Side - (BaE Systems), CH2M Hill, Site Redevelopment Project

START Date: 
November, 2016
END Date: 
October, 2017

November 2016 to October 2017: CH2M Hill – Senior Planning Engineer

·         Working as part of a Consultancy team supporting BaE Systems on an £800m portfolio of  Security Sensitive works

·         Introducing Project Control measures to support the individual projects

Experience Hours (Planning & Scheduling): 
2100
Experience Hours (Cost Management): 
500