Planning & Project Control Engineer, Punj Lloyd Limited, 34" Gas Transmission Pipeline Projects

START Date: 
November, 2006
END Date: 
February, 2008

Ø  Planning and scheduling, Developing and updating Project Control and Progress Measurement Methodology, Establishing and maintaining the projects plans and ensure that all plans are consistent for both parallel running projects. Review Vendor schedules and identifying the critical path.

Ø  Coordinating with Engineering subcontractors and vendors from across the Europe, Asia and other international locations.

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
2500

Planning Engineer, Tecnimont ICB Pvt. Limited, Panipat Naphtha Cracker Project

START Date: 
March, 2008
END Date: 
February, 2009

Project Executed

Ø    Panipat Naphtha Cracker Project (EPCC-2A) Polypropylene Unit (Design Capacity- 2x300,000 TPA, Basell Spheriphol Technology) and Product Warehouse & Bagging Units (LSTK Project) Owner Indian Oil Corporation Limited (IOCL) and Project Management Consultant Engineers India Ltd. India.

Major Responsibilities

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000

Project Engineer, Westfield, LLC, Roseville Galleria Mall Project

START Date: 
May, 2007
END Date: 
August, 2009

Project Engineer, Westfield, LLC (Roseville Galleria Project, CA)

• Worked for the largest retail investment group in the world on a $150 M

Market Place