PROGRESS UPDATE

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date: 
January, 2013
END Date: 
May, 2014

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2500

Project Control Engineer, EC Harris (part of Arcadis Group), Heathrow Terminal 2A

START Date: 
January, 2013
END Date: 
May, 2014

I am responsible for project controls of all M&E services deliverables of T2A Project in Heathrow Airport.  My client is the M&E Delivery Lead of Heathrow Airport Limited.  I produce periodic & monthly control management reports to the client, to reflect main contractor’s delivery and cost performance.  This is by validating progresses via regularly attending and influencing various deliveries / interface meetings and to ensure that not only contractors and sub-contractors are working to the delivery target deadlines but working in this busy environment whilst ove

Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
2500

Senior Planning Engineer, FSB , SUB STATION & INFRASTRUCTURE

START Date: 
March, 2006
END Date: 
March, 2012

RESPONSIBILITIES:

1. Prepare Program
Set up project calendar
Set up Activities and Coding with construction managers
Set up resource requirements using standard outputs
Sequence & link the required activities, within given milestones.
Establish the critical path through the program
Prepare information schedule in conjunction with construction manager
Prepare subcontract appointment schedule with construction manager

Senior Planning Engineer, FSB, SUB STATION & INFRASTRUCTURE

START Date: 
March, 2006

RESPONSIBILITIES:

1. Prepare Program
Set up project calendar
Set up Activities and Coding with construction managers
Set up resource requirements using standard outputs
Sequence & link the required activities, within given milestones.
Establish the critical path through the program
Prepare information schedule in conjunction with construction manager
Prepare subcontract appointment schedule with construction manager