Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Primavera P6

Lead Planning & Scheduling, CH2M Hill, 2022 FIFA World Cup Qatar

START Date: 
January, 2013

Program  : 2022 FIFA World Cup Qatar
Client  : Supreme Committee for Delivery & Legacy (SCDL)
My prime responsibility is proactively managing, controlling and reporting on the planning and scheduling activities to support Infrastructure Assurance team as they provide assurance to SCDL.
Key stakeholders and the broad infrastructure projects monitored for assurance are:
Key Stakeholder Organisation Infrastructure Projects Monitored for Assurance
Ashghal Expressway, Sharq Crossing, Local Roads & Drainage
Qatar Rail Metro Phase 1

Senior Scheduler / Planner, BECHTEL, KPIZ – Khalifa Port & Industrial Zone ( Package 1000-208 Onshore Civils and Buildings)

START Date: 
March, 2010
END Date: 
January, 2013

Project  : KPIZ – Khalifa Port & Industrial Zone ( Package 1000-208 Onshore Civils and Buildings)
Client  : ADPC – Abu Dhabi Ports Company
Value  : Package value US $ 405 million
Commencing March 2010, I have joined the scheduling team of Bechtel on their Khalifa Port and Industrial Zone (KPIZ) project (US $ 5.4 billion) in Abu Dhabi for which they are the Program Management Consultant.
The contract 1000-208 works consisted of civil and building infrastructure including:

Lead Planner, PARSONS AND BRINCKORHOFF, QATAR RAIL PROJECT

START Date: 
October, 2014
END Date: 
August, 2016

LEAD PLANNER

 

I am currently working as Lead planner in Parsons & Brinckorhoff for Qtar Rail project at Doha Qatar.

Qatar Rail project is a multi billion dollar project .

I am responssible for Programme analysis, progress monitoring, delay analysis, Overall progress analysis for Tunneling & Station construction progress.

Use Primavera 8.2 ,TILOS as programming software. 

Planning & Cost Control Engineer, Intaya Construction Inc, İstanbul Sarayları

START Date: 
March, 2011
END Date: 
March, 2013

Planning & Cost Control Engineer:

  • Establishing work programme
  • Prepearing progress reports
  • Prepearing financial reports
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000

Planning & Cost Control Chief Engineer, Kontek Construction Inc., Head Office (various projects in Russia)

START Date: 
March, 2013
END Date: 
January, 2015

Planning & Cost Control Chief Engineer (head office):

  • Establishment of work programme (level 4, level 5) with Primavera P6.
  • Manpower analysis.
  • Preparing monthly reports.
  • Preparing Financial Reports.
Experience Hours (Planning & Scheduling): 
3850
Experience Hours (Cost Management): 
3850

PLANNING ENGINEER, Habtoor Leighton Group (HLG), Dualization of Bidbid Sur Road Project

START Date: 
October, 2014

£  Working as Project Planning Engineer for Habtoor Leighton Group (HLG) in their Bid Bid – Sur Road Project, which is a 6 lane 75 Km long with 13 Bridges and 194 Culverts.

£  Responsible for updating actuals on daily basis in client approved program (using Primavera P6 R7) and to show project progress in Monthly Progress Reports (MPR).

£  Responsible for developing Daily Progress Reports (DPR) for client submission, Weekly KPI (Key Performance Index) Reports for Internal management meetings, and Monthly Project Progress Photographs Reports for Head Office.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
500

PMO Analyst, EC HARRIS, WELSH WATER, Welsh Water PMO

START Date: 
April, 2013

2013-2015 Program Management Office, Welsh Water Capital Program

Alignment of cost and project management business plans to produce a 14-measure dashboard report comprising finance, program delivery, efficiency, health & safety, risk and delivery of regulatory outputs.

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
4100
Experience Hours (Forensic Analysis): 
400

Planning & QS, IL&FS Engineering construction company limited, Mahindra Ashvita Project

START Date: 
December, 2012

Working as Sr. Manager Planning & QS at IL&FS engineering construction company limited since 2012.

Planning & QS, IL&FS Engineering construction company limited, Mahindra Ashvita Project

START Date: 
December, 2012

Working as Sr. Manager Planning & QS at IL&FS engineering construction company limited since 2012.

Sr.Planning Engineer, Galfar Engineering & Contracting Oman, Buildings ,Health Centre,Central Bank Oman & Infrastructure

START Date: 
June, 2011

Project Planning & Project Controls Professional, with expertise in EPC projects life cycle. Worked in Construction Management, Planning and Controls, EVM, Risk, and Procurement/Contracts Administration. 
My involvement over the past years have been in Oman with respect to Health center ,Infrastructure ,High Rise Building projects,  I have been catering to the requirements of the Clients and Consultants for various projects across Oman.

Experience Hours (Planning & Scheduling): 
21150
Experience Hours (Cost Management): 
21150

Market Place

No results found... (try selecting a different content filter)

Syndicate content