Senior Scheduler / Planner, BECHTEL, KPIZ – Khalifa Port & Industrial Zone ( Package 1000-208 Onshore Civils and Buildings)

START Date: 
March, 2010
END Date: 
January, 2013

Project  : KPIZ – Khalifa Port & Industrial Zone ( Package 1000-208 Onshore Civils and Buildings)
Client  : ADPC – Abu Dhabi Ports Company
Value  : Package value US $ 405 million
Commencing March 2010, I have joined the scheduling team of Bechtel on their Khalifa Port and Industrial Zone (KPIZ) project (US $ 5.4 billion) in Abu Dhabi for which they are the Program Management Consultant.
The contract 1000-208 works consisted of civil and building infrastructure including:

Project Controls Director, Astad Project Management, Various Project - Qatar

START Date: 
August, 2014

Responsible

Project Planning and Control,

Budget and Accounts Control,

Document Control,

Reporting Services,

Budget and Plans,

Policies, Systems, Processes & Procedures,

<

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
2000

Senior Project Manager/Engineer, Buro Happold, Ore Valley Village, Hastings UK (2005 – 2007)

START Date: 
June, 2005
END Date: 
August, 2007

Client: South Eastern England Development Authority (SEEDA)

Value: £20m