Planning and Scheduling; Progress Reporting; primavera 3 & 6

Planning / Project Controls Engineer, ICA Fluor Daniel, Samalayuca II Combined Cycle Power Plant

START Date: 
October, 1996
END Date: 
April, 1997

Engineering progress control, Weekly and Monthly Progress Report, Engineering Schedule tracking

Experience Hours (Planning & Scheduling): 
1050

EPC Senior Planner, Pentech Ibérica, Tenders to Oman Oil and Mozambique.

START Date: 
November, 2013
END Date: 
August, 2016

Pentech Ibérica. Planning&Control Manager for Middle East and Africa. Internal consulter/trainer of Primavera, SAP and Risk on Infrastructure Construction. Tenders to EPC projects.

Experience Hours (Planning & Scheduling): 
550
Experience Hours (Cost Management): 
750
Experience Hours (Forensic Analysis): 
200

Campaign Planning Engineer, Aker Solutions (seconded), Brunei Offshore Reliability, Maintenance and Construction

START Date: 
April, 2010

 

ZAINAL DAUD SENDIRIAN BERHAD

(Seconded to AKer solutions)

PLANNING ENGINEER

JAN 2013  – PRESENT

 

Develop, update and maintain project plan (Level 4)

  • Update and maintain Level 4 activities that include task management, engineering, procurement, construction, installation and completion act