Planning Engineer, Pureworld Middle East - Abu Dhabi, Inter Refinery Pipeline – II Client:TAKREER, Oily Water Sump Project - Habshan Facilities - Client:GASCO, Construction of Cathodic Protection of Well Casing - Client: ADCO

START Date: 
July, 2011
END Date: 
November, 2013
• Preparation of Planning Package as per agreed Schedule and WBS Structure.• S Curve Preparation.• Preparation of Effective Project Progress Monitoring System.• Weekly, Monthly and Daily Report Preparation for Client and Management.• Review of Project Progress with Project Construction Team so as to notify of any deviation and corrective actionpreparation.• Project Budget and Cash Flow Preparation.• Project Cost Control and Reporting.• Subcontractor Administrat
Experience Hours (Planning & Scheduling): 
6700
Experience Hours (Cost Management): 
1900
Experience Hours (Forensic Analysis): 
850