Project Engineer, Betathorne Ltd., Multiple Projects

START Date: 
May, 1989
END Date: 
May, 1992

Project Engineer for multiple Projects in the petrochemical and oil and gas industry

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
1000

Project Engineer, John Boyd Associated, Multiple Projects

START Date: 
May, 1992
END Date: 
May, 1994

Project Engineer on Multiple Projects in the Petro Chemical industry

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
500

PROJECT MANAGER, DAR AL RIYADH Consultants, Multiple Projects

START Date: 
May, 1994
END Date: 
May, 2000

Project Management on Multiple Projects in Oil & Gas Industry

Experience Hours (Planning & Scheduling): 
12000
Experience Hours (Cost Management): 
3000

Planning Engineer, SINOTEC CO., LTD, Marala Hydro Power Project (8MW), Daralkhwar Hydropower Project (36MW)

START Date: 
September, 2013
  • Preparation of  EPC Base line Schedules (Civil, Mechanical and E&I)
  • Monitoring of Projects
  • Preparation of Monthly and Weekly Reports for Clients
  • Preparation of Look ahead Plans
  • Earned Value Management (EVM)  and S-Curve analysis for monthly and weekly meetings
  • Estimation of Resources

Planning Engineer, Peaks Group, Jeddah Saudi Arabia, infection desies Hospital

START Date: 
January, 2006

Preparation of Plan of given quantities of a project.

Monitoring and supervision of pallned activities.