Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

%26 Project Planning; Progress Reporting; Claims

Associate and Claims Planner (Senior), Samsung C & T Engineering & Construction, HUB office Building & 3km road and Utilities Project

START Date: 
January, 2015
END Date: 
February, 2016

Senior Planning Engineer

Project Name:HUB office Building & 3km road and Utilities Project

Project Value:(QAR 269 Million)

Client:Lusail Real Estate Development Co.

Responsibilities:

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
2000

Planner, TBH, Perth Childrens Hospital

START Date: 
January, 2015

Perth Children's Hospital. Project Planner and Forensic Claims Consultant: P6 As Built Analysis. P6 Planning of Variations works. Contractual and quantum analysis of PrRospective Delays

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
2000

Planner, TBH, Perth Childrens Hospital

START Date: 
January, 2015

Perth Children's Hospital. Project Planner and Forensic Claims Consultant: P6 As Built Analysis. P6 Planning of Variations works. Contractual and quantum analysis of PrRospective Delays

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
2000

Planner, TBH, Perth Childrens Hospital

START Date: 
January, 2015

Perth Children's Hospital. Project Planner and Forensic Claims Consultant: P6 As Built Analysis. P6 Planning of Variations works. Contractual and quantum analysis of PrRospective Delays

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
2000

Airport Planning Consultant, TBH Group, Perth International Airport project

START Date: 
October, 2014
END Date: 
October, 2015

Perth Airport Expansion

Role: Planner/Lead Planner

Duties: Maintaining/Statusing construction program, developing commissioning program, progress reporting, EOT claims

Experience Hours (Planning & Scheduling): 
9000

Planning Consultant, First Line Consultancy, (various projects)

START Date: 
April, 2008
END Date: 
November, 2009
  • Prepare Preliminary Project Construction Programme & Method Statement for Tender submissions.
  • Prepare detailed programme & Method Statement for Construction.
  • Conduct Meeting with site engineer’s for reviewing progress.
  • Update the Construction Schedules.
  • Prepare delay-notices to Engineer in regards to Employer’s delay events.
  • Conduct delay analysis and prepare Detailed Particulars (Contractor’s claims) for Extension of Time using recognised construction industry methods applicable to the contract conditions.
  • Review and provide resp
Experience Hours (Planning & Scheduling): 
1250
Experience Hours (Forensic Analysis): 
2000

Quality & Planning Engineer, Jubaili Bros Engineering Ltd, Site Integrated Maintenance Scheme (SIMS)

START Date: 
November, 2007
END Date: 
June, 2011

·         Ensured all engineering work is completed on schedule, on budget and in accordance with client and company established work procedures and quality.

·         Coordinated with Project Teams on all Quality aspects and ascertained works meets all practical, commercial, requirements of productivity and quality targets.

Experience Hours (Planning & Scheduling): 
1800

Planning and Coordination Manager, Planitec, New Streetcar line (T6 from Châtillon to Vélizy)

START Date: 
August, 2012
END Date: 
December, 2013

Planning & Coordination Manager – Setec Industries – Vélizy - France

Plannification and coordination manager on a new tramway project (T6 line, southern Paris). Total cost : 384 millions of €

Experience Hours (Planning & Scheduling): 
2850

Project Quantity Surveyor , Contracting & Construction Enterprises Ltd., SAUDI RAILWAYS ORGANIZATION (SRO)Riyadh City, KSA: RUNNING REPAIR SHED, HEAVY REPAIR WORKSHOP

START Date: 
July, 2012
END Date: 
July, 2013

·         Prepared detailed takeoffs from division 2 to division 13.

·         Advised and coordinate the procurement Engineer on procurement strategy.

·         Prepared a cost price breakdown for a new works not included in the BOQ.

·         Revised cost price breakdown for potential savings.

Experience Hours (Cost Management): 
14000

Senior Project Manager / Consultant, PPM Project Managers, High rise Buildings

START Date: 
February, 2008
END Date: 
December, 2014

Current Role

Manage Project Managers and developments within budget, on programme and with good quality and ensure compliance with all statutory, building regulations and procurement guidelines.

Report to directors in South Africa on all projects in Ghana.

Analyse and manage new development opportunities to maximise the returns for the company and unlock the value of vacant land and bulk in hand.

Value engineering of developments or redevelopments concepts and refinement to ensure future proofing of the investment.

Experience Hours (Planning & Scheduling): 
10700
Experience Hours (Cost Management): 
10950
Experience Hours (Forensic Analysis): 
100