Bid/Project Planning Engineer, Almoayyed Air Conditioning Qatar, Vendome Mall

START Date: 
September, 2015
  • Study the contract documents and understand the nature of the job along with start date and end date.
  • Review the IFC drawings along with the PE for an understanding of the scope of works.
  • Prepare the project charter and study the BOQ for program preparation
  • Prepare the works program (WP) along with cost and labor loaded in discussion with PE,PM and Higher level management in 14 days from the date of receiving the main contractor program, and follow up main contractor for the approved program and should u

Bid/Project Planning Engineer, Almoayyed Air Conditioning Qatar, Vendome Mall

START Date: 
September, 2015
  • Study the contract documents and understand the nature of the job along with start date and end date.
  • Review the IFC drawings along with the PE for an understanding of the scope of works.
  • Prepare the project charter and study the BOQ for program preparation
  • Prepare the works program (WP) along with cost and labor loaded in discussion with PE,PM and Higher level management in 14 days from the date of receiving the main contractor program, and follow up main contractor for the approved program and should u

Bid/Project Planning Engineer, Almoyyed air Conditioning, Vendome Mall

START Date: 
September, 2015
  • Study the contract documents and understand the nature of the job along with start date and end date.
  • Review the IFC drawings along with the PE for an understanding of the scope of works.
  • Prepare the project charter and study the BOQ for program preparation
  • Prepare the works program (WP) along with cost and labor loaded in discussion with PE,PM and Higher level management in 14 days from the date of receiving the main contractor program, and follow up main contractor for the approved program and should u

Advisor - Planning and Scheduling, Maks automation, Design of Automatic pick and place robots

START Date: 
May, 2013
END Date: 
May, 2015
  • Prepare the Daily, Weekly and Monthly reports
  • Prepare the baseline program and update the work progress as per the contract
  • Monitor the site activities as per the baseline program
  • Monitor and tracking the delivery of materials
  • Ensured that all site operations were carried out in safe productive manner
  • Monitor critical activities based on the project schedule and advise project management.
  • Report to the Project Manager about the cu

Senior Planner, AMEC, Paisley Council Headquaters

START Date: 
October, 2005
END Date: 
October, 2006

Senior Site Planner for Amec building New extension and full exisiting structure refurbishment of Paisley Council HQ (Value £40) Responsible for all planning duties including progress reporting and short term target planning Assisting Commercial department with procurement and delay analysis

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
200

Planning Engineer, M/s NAGARJUNA CONSTRUCTION COMPANY INTERNATIONAL LLC, NOCL Oil Refinery

START Date: 
June, 2009
END Date: 
July, 2010

Worked as planning engineer for NOCL refinary project in cuddalore Tamilnadu, India

 

Monitored the mobilization works such as site office construction ,batching plant erection.

Experience Hours (Planning & Scheduling): 
1450
Experience Hours (Cost Management): 
1800
Experience Hours (Forensic Analysis): 
2600

Project Planner Primavera P6, Niplan Engenharia, Pellet Plant Project VIII - Phase 2 –Company: Vale S / A

START Date: 
June, 2013
END Date: 
November, 2013
Notifying project changes to the planning manager through the Reports with time analysis (deadline) current timeline x Baseline;Analysis of HH Index and consumed and allocated Material to accomplish the scheduled weekly Work packages;Submission of weekly scheduling of work packages to be executed;Updating and rescheduling activities on the current timeline;Impacts analysis due to the rescheduling of work packages in Project conclusion;Generate critical project path report;Action Plan study for the implementation of the proj
Experience Hours (Planning & Scheduling): 
900
Experience Hours (Forensic Analysis): 
900

Project Planner Primavera P6, CIRJ - Consórcio Integrador Rio de Janeiro - (Odebrecht/CH2M Hill Consortium), Infrastructure Project RIO 2016 Olympic Games

START Date: 
February, 2014
END Date: 
November, 2014
Supervision of schedules of engineering stages, bidding, supply, Construction, electromechanical assembly and commissioning;Time Analysis (deadline)-Enterprise physical timeline advancement Builder x Baseline Timeline of management.Elaboration and timeline control of engineering stages, Bidding, supply, Civil, electromechanical assembly and Commissioning;Elaboration of Time Deviation report (deadline) Physical advancement Physical timeline of the company builder x timeline Baselinemanagement;Scope analysis (inclusion/exclusion) study
Experience Hours (Planning & Scheduling): 
1600
Experience Hours (Forensic Analysis): 
1600

Planner Project, SGS, Puma Klabin Project

START Date: 
April, 2015
END Date: 
January, 2016
Notifying the commissioning team the released engines for testing of Cables Continuity (Electric room x field); Physical infrastructure, Advancement Report, cable launch; Connecting cables in motors and instruments, Assembling Electrical equipments and instruments;Critical Path Analysis – Interface between the phases of Civil construction, Mechanical, electrical, instrumentation, automation and commissioning;Issuance and Upload Check-List electrical assembly of motors, panels and Instruments in the system Pims completion Valpro;Issuance of Labor histogram.
Experience Hours (Planning & Scheduling): 
1550
Experience Hours (Cost Management): 
1550
Experience Hours (Forensic Analysis): 
1550

Assistant Project Manager / Project Planner, ARC Investimentos e Controle, Management of Mondelez International Engineering Projects

START Date: 
July, 2016
END Date: 
September, 2017
Engineering Project Management (adjustments to the Plant safety systems, automation of Chocolate production lines.Issuing managerial report (Curve S) with physical progress information of the projects, WBS Physical x Financial * Elaboration and timeline control of the stages of Civil construction, electromechanical assembly, instrumentation, automationand Commissioning; Elaboration of time-deviation report (Term) Physical advancement Physical timeline of the construction company x managerial Baseline Schedule; * Scope analysis (inclusi
Experience Hours (Planning & Scheduling): 
2400
Experience Hours (Cost Management): 
2400
Experience Hours (Forensic Analysis): 
2400